1. Activity duration estimate inputs include all of the following except:
A. Resource requirements.
B. Basis of estimates.
C. Activity lists.
D. Constraints.
2. All of the following are contract types except:
A. Unit-price.
B. Make-or-buy.
C. Cost reimbursable.
D. Lump sum.
3. Initiation inputs for a project include all of the following except:
A. Product description.
B. Strategic plan.
C. Project charter.
D. Selection criteria.
4. Responses to risk threats include all of the following except:
A. Avoidance.
B. Acceptance.
C. Mitigation.
D. Rejection.
5. The process of performance reporting includes all of the following except _____________.
A. Status reporting.
B. Progress reporting.
C. Forecasting.
D. Product analysis
6. Constrained optimization methods of project selection include:
A. Scoring models.
B. Benefit-cost ratios.
C. Multi-objective programming algorithms.
D. Subjective analyses.
7. Which of the following statements concerning contract type is correct?
A. A fixed price contract contains the most risk for the buyer.
B. Cost reimbursable contracts offer sellers the highest profit potential.
C. Lump sum contracts offer sellers the greatest profit potential.
D. Unit price contracts are illegal in many jurisdictions.
8. A Work Breakdown Structure (WBS) numbering system should allow project staff to:
A. Identify the level at which individual WBS elements are found.
B. Identify configuration management milestones.
C. Estimate the costs of WBS elements.
D. Provide project justification.
9. All of the following are true quality statements except:
A. Quality improvement depends upon better definition and increased awareness of the
requirements/specifications.
B. Project quality management must address both management of the project and the product of the project.
C. Recognition of key actions required of each team member is necessary to meet quality objectives.
D. Computer-aided design systems can improve quality, but only at the expense of an increase in the cost of design.
10. All of the following are examples of tools often used in cost estimating except:
A. Parametric modeling.
B. Analogous estimating.
C. Bottom-up estimating.
D. Activity duration estimates.
11. At XYZ Inc., the hourly wage for semi-skilled workers is $14.00. The annual audit shows that fringe benefits cost 30% of basic wages, and that overhead costs are 60% of wages plus fringe benefits. What is the loaded” hourly wage for a semi-skilled worker at XYZ Inc.?
A. $27.14.
B. $28.96.
C. $30.03.
D. $29.12.
12. Of the following estimates, which most accurately reflect the actual cost of the project?
A. Conceptual estimates.
B. Order of magnitude estimates.
C. Preliminary estimates.
D. Bottom-up estimates.
13. The most crucial time for project risk assessment is:
A. When a problem surfaces.
B. During the planning phase.
C. During the close-out phase.
D. After the project schedule has been published.
14. When there is uncertainty associated with one or more aspects of the project, one of the first steps to take is to:
A. Revise project plan.
B. Conduct a risk-benefit analysis.
C. Conduct a needs analysis.
D. Increase the estimated cost of the project.
15. Including a contingency reserve in the project budget is intended to:
A. Reduce the probability of scope changes.
B. Increase the probability of scope changes.
C. Reduce the probability of a cost overrun.
D. Increase the probability of a cost overrun.
16. Given the information in the following table, what is the expected value from this risk event? Probability Result
A. -10,000.
B. - 7,500.
C. + 2,500.
D. -7,000.
17. A contractor is working on a fixed price contract that calls for a single, lump sum payment upon satisfactory completion of the contract. About halfway through the contract, the contractor project manager informs their contract administrator that financial problems are making it difficult for them to pay their employees and subcontractors. The contractor asks for a partial payment for work accomplished. Which of the following actions by the buyer is most likely to cause problems for the project? A. Starting partial payments for work accomplished.
B. Making no payments because it would violate the conditions of the contract.
C. Paying for work accomplished to date.
D. Negotiating a change to the payment conditions in the contract.
18. A precise description of a physical item, procedure, or service for implementation of an item or service is called :
A. Work package.
B. Baseline.
C. Product description.
D. Work breakdown structure (WBS) element.
19. A project should be terminated for all of the following reasons except:
A. Lack of team synergy.
B. The project no longer meets the company’s objectives.
C. The resources are not available to complete project activities.
D. Project funding has been significantly reduced.
20. One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and:
A. Divide it by the schedule performance index.
B. Multiply it by the schedule performance index.
C. Multiply it by the cost performance.
D. Divide it by the cost performance index.
参考答案:
1.B 2.B 3.C 4.D 5.D 6.C 7.C 8.A 9.D 10.D 11.D 12.D 13.B 14.B 15.C 16.D 17.B 18.C 19.A 20.D
- 1内蒙古科尔沁右翼前旗为城区路灯上“户口”
- 2[安徽]城市Ⅰ级主干道改造工程基层施工方案(中铁)
- 3无粘结预应力平板结构施工
- 4一级建造师复习资料:免责条款无效情况
- 5谈煤矿企业安全文化建设
- 6浅谈无负压供水设备在现代居住小区中的推广与应用
- 7山西省2015年二级建造师考试报名费用
- 8我国环境保护工作的基本方针——三十二字方针是什么?
- 92015造价员《安装工程》知识点:炉墙的砌筑
- 102015年招标师项目管理:工程建设项目管理承包模式
- 11江苏推行智能建筑工程质量检测、验收规范
- 12不锈钢矩形风管制作工法
- 13 用心感受幸福
- 14钢桁梁现场栓焊混合连接施工工艺
- 15滨州2015年招标师考试报名费用发票事宜
- 1609年安全工程师辅导:煤矿灾害预防和处理计划(4)
- 17照明设计基础名词解释
- 18大庆市2015年咨询工程师报名条件
- 19陕西2015年招标师考试报名时间:6月22日-7月17日
- 20用项目管理软件作一完整项目计划,求推荐!
- 21项目建议书阶段
- 22一级建造师法规及相关知识复习要点:质量要求
- 23农业综合开发土地治理项目施工组织设计方案30p
- 242015年无锡造价工程师工资待遇
- 25考一建还是造价工程师
- 26招标师专业实务第四章命题点:工程建设项目监理和项目管理服务招标
- 27沟通,制定绩效指标的“攻关员”
- 28油溶性聚氨酯化学灌浆材料
- 29山东省二级建造师注册有效期及继续教育标准
- 30造价工程师复习资料:建筑面积计算规则
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼