项目管理师考前模拟试题(一)及参考答案
1. A narrative description of products or services to be supplied under contract is called:
A. The project plan.
B. A statement of work.
C. An exception report.
D. A Pareto analysis.
2. An example of scope verification is:
A. Reviewing the performance of an installed software module.
B. Managing changes to the project schedule.
C. Decomposing the WBS to a work package level.
D. Performing a benefit/cost analysis to determine if we should proceed with the pro
3. Which of the following is not an example of a source of scope change?
A. A variation in government regulations.
B. Failure to include a required feature in the design of a telecommunication system.
C. A need to engage in bottom-up cost estimating.
D. Introducing technology that was not available when scope was originally defined.
4. The subdivision of major project deliverables, as identified in the scope statement, into smaller, more manageable components is called:
A. Parametric estimation.
B. Scope definition.
C. Feasibility analysis.
D. Benefit-cost analysis.
5. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called:
A. Strategic planning.
B. Alternative objectives inventory.
C. Management by objectives.
D. Contingency planning.
6. Configuration management is:
A. Used to ensure that the description of the project product is correct and complete.
B. The creation of the work breakdown structure.
C. The set of procedures developed to assure that project design criteria are met.
D. A mechanism to track budget and schedule variances.
7. A fundamental tenet of modern quality management holds that quality is most likely to be achieved by:
A. Planning it into the project.
B. Developing careful mechanisms to inspect for quality.
C. Striving to do the best job possible.
D. Conducting quality circle activities.
8. Your most recent project status report contains the following information: BCWP = 3,000, ACWP = 3,500, and BCWS = 4,000. The schedule variance is:
A. + 1,000.
B. + 500.
C. - 500.
D. - 1,000.
9. Learning curve theory emphasizes that in producing many goods:
A. Cost decreases as production rates increase.
B. Average unit cost decreases as more units are produced.
C. Materials become cheaper when they are purchased in bulk.
D. Laborers become more productive because of technological advances.
10. Rearranging resources so that constant resource levels are maintained is called:
A. Floating.
B. Leveling.
C. Restructuring.
D. Crashing. 11. The _________ is a time-phased budget that will be used to measure and monitor cost performance in the project.
A. Work breakdown structure
B. Project schedule
C. Cost baseline
D. Cost budget
12. To transfer most of the cost risk to the contractor, the client may use a ___________ contract.
A. Cost plus award
B. Cost plus incentive fee
C. Cost plus fixed fee
D. Fixed price
13. An appropriate sequence for risk management activities is:
A. Risk identification, risk quantification, and risk response development and control.
B. Risk identification, risk assessment, and risk planning.
C. Risk identification, risk mitigation, and risk management.
D. Risk identification, risk elimination, and risk mitigation.
14. Theory X holds that:
A. Quality improvements lie in the hands of quality circles.
B. Profits are tied to meeting schedule deadlines.
C. Absenteeism is tied to poor working conditions.
D. Workers are inherently unmotivated and need strong guidance.
15. All of the following are characteristics of parametric estimating except:
A. Historical information.
B. Quantifiable.
C. Scalable.
D. Activity lists.
16. Inputs to cost budgeting include all of the following except:
A. Cost baseline
B. Cost estimate
C. Work breakdown structure
D. Project schedule
17. Inputs used during scope planning include all of the following except:
A. Constraints.
B. Project charter.
C. Budget/cost analysis. D. Product description.
18. Cost control outputs include all of the following except:
A. Estimate at completion.
B. Budget updates.
C. Revised cost estimates.
D. Cost baseline.
19. Risk identification outputs include the following except:
A. Decision trees.
B. Inputs to other processes.
C. Risk symptoms.
D. Potential risk events.
20. Puts into overall change control include all of the following except:
A. Project plan.
B. Change requests.
C. Change control system.
D. Performance reports
参考答案:
1.B 2.A 3.C 4.B 5.C 6.A 7.A 8.D 9.B.10.B 11.C 12.D 13.A 14.D 15.D 16.A 17.C 18.D 19.A 20.C
- 1二级建造师资格证书不予注册的理由及需要补充的材料
- 22010年上半年建筑生产安全事故情况通报
- 3给水排水工程大学专业排名
- 4怎样掌握天然花岗石的特性?
- 5河北省青县土地开发整理示范项目规划设计报告
- 6项目标准化管理手册
- 7防雷设计中的接地问题
- 8一级建造师市政公用工程管理与实务复习要点:混凝土路面
- 9青海5年内对既有公建实施抗震加固
- 10一级建造师管理与实务复习要点:非常规起重设备
- 11国务院:27项全国重大水利工程已开工22项
- 122015年二级注册消防工程师考试《综合能力》备考资料(9)
- 13一级建造师法规及相关知识复习要点:代理
- 14该如何备考2008年注册造价工程师执业资格考试?
- 15PVC防水卷材屋面工程施工控制
- 16632项行政审批事项被取消和下放 下一步要注重管放结合
- 17某工程环境因素台帐
- 18住房城乡建设部、文化部、财政部要求加强传统村落保护发展工作
- 19义乌市2015年度二级建造师考试报考条件
- 20幕墙工程施工工艺标准(新ZS-10-全套)
- 21建设工程项目管理:建设工程现场职业健康安全卫生的要求
- 22吉林推进建筑废弃物综合利用
- 23一级建造师复习资料:机电工程施工图设计阶段的管理要求
- 24郑州新修马路怎么说塌就塌了?
- 25一级建造师复习资料:施工单位应当承担的消防施工质量和安全责任
- 26钢纤维混凝土隧道的耐久性能研究
- 272015年造价员考试《土建工程》知识点:土石方工程施工
- 28全国“治违行动”号声响起
- 294月房屋市政工程事故同比减少
- 302015年咨询工程师《工程咨询概论》第十章(5)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼