监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 甲方项目管理系统 | 签约案例 | 客户案例 | 在线试用
X 关闭
建筑工程项目管理软件

当前位置:工程项目OA系统 > 建筑OA系统 > 建筑工程项目管理软件

PMP认证考试试题精选(6.4)以及答案

申请免费试用、咨询电话:400-8352-114

51. The objective of fast tracking a project is to: 
  a. increase productivity. 
  b. reduce project duration. 
  c. accelerate cost tracking. 
  d. mitigate project risks. 

52. Complex projects, involving cross-disciplinary efforts, are most effectively managed by a: 
  a. projectized organization. 
  b. functional organization. 
  c. strong matrix organization. 
  d. strong virtual organization. 

53. You’ve been engaged to manage a project with an estimated cost of ,000,000 that has been publicly approved by the project’s sponsor. Your earned value calculations indicate that the project will be completed on time and under budget by 0,000. Based on this calculation, your personal profit will decrease by ,000. You should plan to: 
  a. invoice for the full amount because the budget has been made public. 
  b. add features to improve the quality without exceeding the public budget. 
  c. inform the end-user that you can add features without exceeding the budget. 
  d. inform the project sponsor of the projected financial outcomes. 

54. One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and: 
  a. divide it by the schedule performance index. 
  b. multiply it by the schedule performance index. 
  c. multiply it by the cost performance. 
  d. divide it by the cost performance index. 

55. Project sponsors have the greatest influence on the scope, quality, time, and cost of the project during the: 
  a. concept phase. 
  b. development phase. 
  c. execution phase. 
  d. closeout phase. 

56. Ideally, communication between the project manager and the project team members should take place: 
  a. via daily or weekly status reports. 
  b. through approved template forms. 
  c. by written and oral communication. 
  d. through the formal chain of command. 

57. During the project scope planning process, the work breakdown structure should be developed to: 
  a. the sub-project levels by phase. 
  b. the levels determined by the project office. 
  c. levels allowing for adequate estimates. 
  d. cost center levels for budgeting. 

58. Responses to risk threats include all of the following except: 
  a. avoidance. 
  b. acceptance. 
  c. mitigation. 
  d. rejection. 

59. To learn who has approval authority for revisions in scope, a project manager should: 
  a. refer to the resource assignment matrix. 
  b. refer to the change control plan. 
  c. review the original project charter. 
  d. request a copy of the organization chart. 

60. A purchase order represents a: 
  a. cash out-flow. 
  b. project expense. 
  c. commitment. 
  d. capital investment.

61. The process of determining how a risk event will affect the project schedule is called risk: 
  a. identification. 
  b. mitigation. 
  c. simulation. 
  d. assessment.

62. Conflict resolution techniques that may be used on a project include: 
  a. compromising, directing, and withdrawing. 
  b. compromising, smoothing, and withdrawing. 
  c. confronting, directing, and smoothing. 
  d. confronting, smoothing, and withdrawing. 

63. Risk identification outputs include the following except: 
  a. risk triggers. 
  b. decision trees. 
  c. inputs to other processes. 
  d. risk events. 
发布:2007-03-04 10:27    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普建筑工程项目管理软件其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件