2012年pmp考试模拟试题及答案(四)
A Allocates resources to activities to find shortest schedule within fixed resource limits.
B Smoothes out resource requirements by rescheduling activities within their float time.
C Smooths out resource requirements by substituting activities with unassigned resources.
D Attempts to reduce resource requirements within a constraint on project duration
E B or D
E
QUEST A(n) _____ is defined as a specified accomplishment in a particular instant in time which does not consume time or resources.
A Activity
B Event.
C Correlation
D Constant
E Event constrained within planned effort.
B
QUEST Which of the following impacts the critical path?
A Changing the task duration.
B Reduce the free float of an activity.
C Executing a backward pass
D A or B
E None of the above.
A
QUEST The range of time allowed for an activity to be completed in is the _____.
A Planned time (Duration).
B Float time (LS - ES, or LF - EF).
C Critical time (when ES = LS, or EF = LF).
D Scheduled time (LF - ES).
E Event.
D
QUEST Free float is the amount of time that an activity may be delayed with out affecting the _____.
A Early start of the succeeding activities.
B Late start of the succeeding activities.
C Project finish.
D Cost of the project.
E None of the above.
A
QUEST Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.
A 0.5
B 1
C 1.8
D 2.2
E 2.8
C
QUEST In crashing a task, you would focus on:
A As many tasks as possible.
B Non critical tasks.
C Accelerating performance of tasks on critical path.
D Accelerate performance by minimizing cost.
E A and D.
C
QUEST Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task
A 8
B 8.8
C 9.1
D 9.7
E 10.5
B
QUEST Using the WBS in the Special window, an instance of a work package is:
A Build house
B Excavate
C Prepare Foundation
D B and C
E None of the above
E
QUEST All of the following are categories of a milestone in a schedule except:
A End date.
B Contract dates.
C Key events scheduled.
D Imposed dates.
E Task duration.
E
QUEST The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A Increases.
B Is not affected by
C Does not require
D Is heavily dependent upon
E Is the only means of determining
D
QUEST Excessive flexibility in specifying requirements will _____ the likelihood of time overruns.
A Reduce.
B Eliminate.
C Double
D Increase
E Not affect
D
QUEST The key purpose of project control is to:
A Plan ahead for uncertainties.
B Generate status reports.
C Keep the project on track.
D Develop the project road map.
E All of the above.
C
QUEST Fast tracking means to:
A Speed up a project through parallel tasks.
B Swap one task for another.
C Reduce the number of tasks if possible.
D B and C.
E None of the above.
A
QUEST As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:
A Insignificant.
B Reduced.
C Unchanged.
D Increased.
E Doubled.
C
QUEST The purpose of a dummy activity in an activity-on-arrow diagram is to:
A Identify a task that could be replaced by another.
B Take the slack time into account.
C Show a task that is not necessarily needed.
D Denote a milestone.
E Show a dependency relationship.
E
相关推荐:2012年pmp考试模拟试题及答案(三)
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015年招标师考试招标采购案例分析复习指导(31)
- 209年注册安全工程师事故案例分析模拟试题(三十九)
- 32015年安全工程师生产案例模拟练习(3)
- 4黑龙江人事考试网公布2015安全工程师报名时间:6月17日-6月30日
- 5黄土隧道施工方法
- 6肇庆市2015年注册造价工程师报名时间为6月8日至7月2日
- 7采购成本分析预测 内容
- 82015年招标师考试《法律法规与政策》复习资料:第四章8
- 92013年二级建造师《法规及相关知识》每日一练(5.20)
- 10项目竣工验收的条件 主要内容
- 11【招标师考试】项目管理与招标采购第三章:产品的项目设计管理
- 12某大桥上塔柱施工
- 132010年PMP美国项目管理考试习题及答案一
- 142015年造价员基础知识:钢筋计算其他问题
- 15一级建造师管理与实务复习要点:沥青
- 16厦深铁路潮州段率先完成铺轨
- 17银川:今年将新修200公里农村公路
- 1808监理工程师《案例分析》练习题8
- 19一级建造师《建设工程经济》考点解析(15)
- 202015年咨询工程师考试《项目决策分析与评价》模拟试题(六)
- 21深基坑工程施工前应取得的资料
- 22安全工程师《生产管理》考前自测题(8)
- 23世界第二座钢板混合梁 悬索桥全线贯通
- 24四川安县2012年投资审计节约1.72亿建设资金
- 25海南2015年招标师考试培训
- 262013年二级建造师《法规及相关知识》每日一练(11.5)
- 272015年咨询工程师《宏观经济政策与发展规划》每日一练(2.28)
- 28园林景观的施工组织设计
- 292015年安全工程师考试安全生产管理知识练习题(7)
- 302013年二级建造师《法规及相关知识》每日一练(11.22)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼