PMP美国项目管理认证模拟预测习题4
A.Assist the CEO in putting together a benefit/cost analysis to show the need for the project
B.Work with the CEO to get buy-in from the other stakeholders
C.Produce a ranking of all feasible projects, including the assigned project, in a weighted scoring of decision variables
D.Guide the creation of a project charter
1.一个公司的CEO任命项目经理来管理一个很久以来就想进行的项目。项目经理首先应该做什么?
A.帮助CEO进行成本/效益分析来说明项目的必要性
B.和CEO一道去获得其它干系人的支持
C.就所有可行的项目排序,根据决策变量制定权重分数
D.指导建立一个项目章程
2.Planned Duration = 12 months, ACWP = $10,000, BCWP = $14,000, BCWS = $17,500, BAC = $28,000. Based on the above data, if we are now at the end of month 6, then the remaining time needed to complete the project is:
A.6 months
B.8 months
C.9 months
D.4 months
2.根据下表信息,现在是第六个月的结束,完成项目所需的剩余的时间是多少?计划历时=12个月,ACWP=$10,000,BCWP=$14,000,BCWS=$17,500,BAC=$28,000
A.6个月
B.8个月
C.9个月
D.4个月
3.What is the present value of $8,000 received three years from now using a seven percent interest rate?
A.$9,800
B.$6,530
C.$9,680
D.$6,612
3.如果根据7%的折现率,三年以后收到的8000美元的现值是:
A.$9,800
B.$6,530
C.$9,680
D.$6,612
44.Giving a team member a corner office with window view is different that giving him health benefits because a corner office is a:
A.Perquisite
B.Fringe benefits
C.Use of expectancy theory
D.Example of formal power
4.安排一个团队成员在一个能看到风景的拐角办公室不同于给他安排健康福利,前者被称作:
A.特殊待遇
B.边际福利
C.期望理论的应用
D.正式权力的例子
5.Which of the following would NOT be an example of a "fixed cost" outlay as used to calculate a cash break-even point?
A. Rent
B. Depreciation
C. Raw materials
D. Executive salaries
5.在计算现金流平衡点时,下列哪一项不被列入固定成本项?
A.租金
B.折旧
C.原材料
D.总裁薪酬
6. Your project is approximately 66% complete and has progressed according to plan. There are nine teams working on implementation and testing activities. You receive notification that two teams are falling behind relative to the others. The
MOST likely reason for this is:
A.The scope of work has changed.
B.A weak matrix project organization.
C.Unidentified risks.
D.Low morale due to compensation issues.
6.你的项目已经完工66%,并且符合计划。实施和测试活动中有9个团队,你收到通知说,有两个团队相对落后于其它团队,最可能的原因是:
A.范围变更了
B.这是一个弱矩阵组织架构
C.未识别的风险
D.待遇问题产生的士气低落
7.A team member notifies the project manager that his team have finished their deliverables without performing all the associated work packages in the WBS. What should the project manager do first?
A.Immediately communicate the changes to other team members and stakeholders
B.Change the project plan
C.Change the project performance measurement baselines
D.Change the reporting process to get information sooner
7.一个团队成员通知项目经理说,它们团队的项目交付成果完成了,但是没有执行WBS中的某些相关工作包,项目经理应该首先:
A.立即把这一变更告知所有团队成员和干系人
B.改变项目计划
C.改变项目绩效衡量基准
D.改变汇报机制,以便更加快速的获得信息
8.Your customer asks for a small change in the project, which was not budgeted in the project.It is a small effort as compared to the total project and you need the goodwill of the customer for such a multimillion-dollar pipeline project. You will:
A.Refuse to do the work
B.Agree to do the work at no charge
C.Do the work and bill him later
D.Assess the cost and schedule impact and tell them you will decide later
8.你的客户要求一个小的变更,它并没有包括在项目预算以内。和整个项目相比,这只是一个小的工作,而且对于这样一个几百万美元的管道项目,你需要客户的良好信赖。你应该:
A.拒绝这一工作
B.同意免费接受这一工作
C.做这一工作,然后开票
D.评估对进度和成本的影响,告诉他们你随后再作决定
相关试题:
添加应用,免费套题体验
PMP美国项目管理认证模拟预测习题1
PMP考试全真模拟题及答案(样题)
PMP模拟习题汇总(附参考答案)
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015咨询工程师《项目决策分析与评价》测试题(十一)
- 2PHC桩施工时采取的几种预防措施
- 32015年咨询工程师《工程项目组织与管理》每日一练6.10
- 42015年咨询工程师《宏观经济政策与发展规划》每日一练(12.14)
- 5试论信息技术在建筑工程项目管理中的应用
- 6论园林微地形的作用
- 72012《工程实务》:高层建筑施工中的沉降观测
- 82015年咨询工程师《工程咨询概论》考试讲义23
- 92015招标师考试案例分析
- 102013年山西二级建造师注销注册申请表
- 112015年韶关造价工程师考试报名时间为7月11日-8月5日
- 122015年安全工程师考试《事故案例分析》模拟题(5)
- 132015招标师考试教材《招标采购实务》辅导知识点3
- 14安全工程师:报名事项
- 15某基本农田土地整理项目某标段施工组织设计100p
- 16招标师2015法律法规备考
- 17爆破工程中的人工打眼
- 18北京市住建委召开建设工程造价咨询招标代理单位工作会
- 19江西省工程施工招投标资格审查新办法出台
- 202015造价员《安装工程》工程量计算规则:门窗工程
- 21机电产品国际招标投标实施办法(9)
- 222015年监理工程师备考指导:如何集中注意力学习
- 23建设工程施工合同类型的选择 :工程施工工期的紧迫程度
- 242012一级建造师《工程经济》:所得税及其所得税会计的程序
- 25安全工程师安全生产法复习资料——调查报告具有真实性
- 26混凝土输送泵液压性能特点
- 27混凝土质量技术保证措施 内容
- 282个月备考2015年招标师可以吗
- 29搅拌车雨刷器维修保养要点
- 30全站仪三角高程测量方法及精度分析
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼