1. Major difficulties arise when multiple projects need to managed in the functional organizational structure because of-
A. The level of authority of the project manager
B. Conflicts over the relative priorities of different projects in competition for limited resources
C. Project team members who are focused on their functional specialty rather than on the project
D. The need for the project manager to use interpersonal skills to resolve conflicts informally
1. 当多个项目需要在职能组织结构中进行管理的时候,会出现很大的困难,因为:
A. 项目经理的权限有限
B. 不同的项目在竞争有限资源过程中会发生冲突
C. 项目小组成员更关注职能部门的本职工作而不是与项目有关的工作
D. 需要项目经理运用个人交际能力非正式地解决冲突
2. The team you have organized for your new project consists of three people who will work full-time and five people who will support the project on a part-time basis. All team members know one another and have worked together in the past. To ensure a successful project start-up, your first step should be to
A. Meet with each team member individually to discuss assignments
B. Prepare a responsibility assignment matrix and distribute it to each team member
C. Distribute the project plan and WBS to the team
D. Hold a project kickoff meeting
2. 你为新项目组建的项目小组包括三个全职人员和五个兼职人员,所有小组人员相互认识并在过去一起共事。为了项目启动顺利,你的第一步是:
A.同每个小组成员单独会面,讨论任务分配
B.准备一个责任分配矩阵并分发给每个成员
C.将项目计划和工作分解结构分发给小组成员
D.举行项目动员大会
3. One organizational option for improving communications and teamwork is using a fight matrix. This approach also serves to facilitate-
A. Fast-tracking
B. Concurrent engineering
C. Resource leveling
D. Work on geographically dispersed or virtual teams
3. 一个公司为改善沟通和团队协作可以选择使用一个紧缩矩阵的形式把大家组织起来。这种方法还能促进
A. 快速赶工
B. 协作工程
C. 资源平衡
D. 地理上分散或虚拟团队的工作
4. Of the following types of historical information that can be used in risk identification, which is the least reliable?
A. Project files
B. Commercial databases
C. Project team knowledge
D. Lessons learned databases
4. 在以下可用于风险识别的历史信息中,最不可靠的是:
A. 项目的档案
B. 商业数据库
C. 项目小组知识
D. 经验数据库
5. The DeIphi technique is a particularly useful method for identifying risk to
A. Present a sequence of decision choices graphically to decision makers
B. Define the probability of occurrence of specific variables
C. Reduce bias in the analysis and keep any one person from haying undue influence on the outcome
D. Help take into account the attitude of the decision maker toward risk
5.德尔菲技术是特别有用的风险识别方法,目的是:
A. 为决策者提供图表式的一系列决策选择
B. 明确特定变量出现的概率
C. 减少分析过程中的偏见,防止任何人对分析结果施加不正当的影响
D. 有助于将决策者对风险的态度考虑进去
试题推荐:
PMP认证考试最新练习题及参考答案(1-10套)
PMP认证考试最新练习题及参考答案(11-20套)
PMP认证考试最新练习题及参考答案(21-40套)
PMP认证考试最新练习题及参考答案(41-56套)
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015年咨询工程师《宏观经济政策与发展规划》每日一练7.31
- 22015年咨询工程师《宏观经济政策与发展规划》每日一练10.13
- 3一级建造师《建设工程经济》复习资料整理(4)
- 4[江苏]经济适用房工程施工进度计划及施工现场平面布置图(16页)
- 5【招标师考试】项目管理与招标采购第二章:市场准入的法律法规
- 6PMP认证考试最新练习题及参考答案(21-27套)
- 708监理工程师《质量控制》练习题2
- 82015年咨询工程师《工程项目组织与管理》每日一练(1.3)
- 9安全工程师考试辅导资料:安全生产相关法律十二
- 10项目决策分析考点:建设项目经济评价参数
- 11西安某住宅项目临时设施平面布置图
- 122015年安全工程师《事故案例分析》模拟题(12)
- 132015年造价工程师《工程造价计价与控制》习题讲义(7)
- 142015年咨询工程师《工程咨询概论》模拟题(九)
- 15CRTS-Ⅱ型板式无碴轨道底座板施工工法(省级)
- 16[江苏]2008年度造价工程师执业资格考试5月下旬开始报名
- 17断桩在预应力混凝土管桩遇到问题的主要原因
- 18人工挖孔桩护壁保证措施
- 19沥青混凝土路面施工方法
- 202015招标师《招标采购法律法规与政策》试题(6)
- 21堤防隐蔽护岸工程施工规划45p
- 22室内给水管网的布置与敷设
- 232015招标师《项目管理与招标采购》:质量鉴定
- 24【感谢名师】考试通过发感言 一次通关就这么简单
- 25项目质量控制体系的多层次结构
- 26《工程项目组织与管理》:工程项目合同的特点
- 272015年咨询工程师《工程咨询概论》每日一练(11.27)
- 28企业投资项目管理解决方案第五章
- 292015年天津安全工程师考试报名时间为5月26-30日
- 30钢管柱柱芯混凝土顶升施工工法
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼