1. One organizational option for improving communications and teamwork is using a tight matrix. This approach also to facilitate-
Fast-tracking
Concurrent engineering
Resource leveling
Work on geographically dispersed or virtual teams
一个公司为改善沟通和团队协作可以选择使用一个紧密的矩阵. 这种方法还能促进
快速追踪
协作工程
资源平衡
地理上分散或虚拟团队的工作
2. In the weak and strong matrix organizational structures, the primary condition leading to conflict is-
Communication barriers
Conflicting interests
Need for consensus
Ambiguous jurisdictions
在松散和紧密型的矩阵组织结构中, 可能引发冲突的基本条件是什么
a.. 沟通障碍
b. 利益冲突
c. 缺乏共识
d. 权限不明确
3. You are the project manager for a new product your company is launching. Yu realize that for success with this project your team must have-
Access to an appropriate set of skills and knowledge about the product
More senior-level staff available to assist junior-level team members on this initiative
An automated project management information system
Regular status review meetings
你是你们公司正在实施的一个新产品项目的项目经理. 你认识到要使这个项目取得成功,你的团队必须具备
一条适当的获取该产品相关技巧和知识的途径
在项目实施中要争取让更多的高级雇员来帮助级别较低的团队成员
一套自动的项目管理信息系统
经常性的状态评论会议
4. You work for one of the leading manufacturers of country and western apparel. You are managing a project to improve customer throughput and efficiency. Much of the project wok must be done on site and will require the active participation of store employees. Many of these employees are lifelong members of a powerful union that has a reputation for labor unrest. One important component of your schedule must be-
a. A resource capabilities matrix
b. Buffers and reserves
c. A resource calendar
d. A resource histogram,
你正在为一家处于领先地位的西部乡村服装生产商工作. 你正在管理一个以增加顾客接待量和效率为目的零售商店布局重新设计的项目. 这个项目的许多工作都要在现场完成,而且需要商店员工的积极参与. 而这些员工中有很多都是一个以鼓动劳工闹事而著称的终生会员. 那么你的进度安排中的一个重要的组成部分必定是
一个资源矩阵
缓存和储备
一个资源筹集日程
一个资源柱状图
5. You are part of a team that is preparing a project plan for your company’s new wireless VCR product line. The team is reviewing a number of items as it prepares the plan. Which one of the following is an example of a project plan development constraint that you should consider as you develop multiple elements of the plan?
Records of past performance
Financial reports from similar projects
Predefined budget
Lessons learned from previous projects
你是一个正在编制项目计划的团队的一员,这个项目是关于你们新型无线录像机产品生产线的开发项目. 在准备这个计划的时候,团队回顾了一系列的计划条款. 在你编制计划的多个部分的过程中,下列哪项是你编制项目计划必须要考虑到的约束条件?
以往的业绩记录
类似项目的财务记录
预先确定的预算
从以往项目中吸取的经验教训
6. Which of the following would you least consider when making a buy decision?
Cost/price
Supplier skills
Standard purchase order terms and conditions
Degree of integration of the purchased goods or services with the project
当作外购决策时, 最不可能考虑下列哪一项?
成本/价格
供应商技能
标准的采购定单的条款和条件
所采购的商品或服务与项目的整合程度
7. Which of the following is not part of the purchasing cycle?
Obtain vendor capabilities
Prepare and issue purchase order
Install purchased equipment
Evaluate proposals
下列哪一项不属于采购阶段?
获得卖主的生产能力
准备和签发采购定单
安装所采购的设备
评估提议
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015招标师《招标采购项目管理》知识点整理3
- 2广西建成一座山顶机场 跑道为世界最窄
- 3招标师法律法规:选择评标专家的原则
- 4沉井泵房施工组织设计17P
- 5温岭市大力实施农村危旧房改造切实改善农民居住环境
- 6安全工程师相关法律知识复习要点:故意破坏现场
- 72015年招标师考试招标采购专业实务考前复习指导(93)
- 8湖南省2015年注册安全工程师考试报名时间为4月1日-10日
- 9秦岭某隧道施工组织设计
- 10过去10年曾出现3次绝佳买房机会 第4次正到来
- 11钢筋混凝土打入桩施工工艺标准
- 12湘桂铁路黎塘至南宁段扩能改造工程某隧道施工组织设计
- 13公路绿化施工组织方案
- 14部分品牌涂料被指编造“抗甲醛”功能
- 15安全生产法律法规模拟试题
- 162015年招标师考试招标采购专业实务考前复习指导(107)
- 17安全工程师辅导资料:二次回路传动试验的安全事项
- 182015年招标师招标采购专业实务考点分析13
- 19湖南机械出租混凝土输送泵的售后人员介绍了混凝土泵车保养、检修及维护工作的要点
- 20二级建造师法规知识点:物权的种类
- 212015年一级建造师《公路工程》公路工程合同管理(4)
- 22安全工程师辅导资料:电力生产中危险点的查找与预控2
- 23湖北省2015年安全工程师考试报名时间确定:4月15日至24日
- 24中国高铁技术连获各国青睐 价格优势无可比拟
- 252015年招标采购专业辅导:项目采购方式及其适用条件
- 262015年造价员基础知识:竣工决算的内容
- 27二级建造师考试复习总结:交通工程机电系统的构成与功能(2)
- 282015年安全工程师考试《生产技术》:急性中毒的现场抢救
- 292015年咨询工程师《项目决策分析与评价》每日一练5.21
- 30安全工程师辅导资料:三相负载不平衡运行对变压器的危害
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼