PMP认证考试练习题(四)(中英文)
1. In order to approve a project, management using simple, as well as complex, sophisticated tools to determine how the project fits into it’s strategic plan. When the project selection includes an in-depth analysis, using complex, sophisticated tools, is os considered to be part of what project phase?
Implementation
Termination
Conceptual
Operational
None of the above
为了批准项目,管理层使用简单的,但同复杂技术的一样好的,久经考验的工具测量项目如何满足它的策略计划. 当项目选择一个包含有深层次分析的,复杂的,久经考验的工具时,它发生在项目的那一个阶段?
执行
终止
概念上
运做
上述都不是
2. What is the most accurate method of obtaining project information that can reduce the amount of risk?
Observations on the current project
Determining the risk by using painstorming techniques
The use of historical data from previous projects that were similar in nature
Sensitivity analysis
Delphi technique
那一个是获得项目信息以降低项目风险总量的最精确的方法?
观察当前项目
应用集体讨论方法决定风险
使用以前类似项目的历史数据
敏感分析
Delphi 技术
3. Contained within the first step of a five step process to determine the risk analysis of the project’s risk events, a process of ________ is performed to see if the risk should be included or excluded as part of the project scope.
Determining the probability
Contingency effort
Assessing the consequences and severity
Screening
在5步过程的第一步内,下列那一个过程是决定项目风险事件的风险分析,它被用于判断风险是否应当作为项目范围的一部分包括在内或不在内.
可能性决定
应急措施
评估因果关系和严重程度
放映
4. A project of 2 million has an adverse event that has the probability of 50% of occurrence and a potential loss of $20,000. This represents an expected negative value of:
$100,000
$1,000
$100
$10,000
一个2百万的项目隐含有一个不利的影响,它发生的可能性是50%,潜在损失是2万. 它的预期负值是多少:
$100,000
$1,000
$100
$10,000
5. The assigned values of risk for a project is best accomplished through a structured methodology that ensures all project elements are evaluated. The project tool that is best suited for the structured analysis of the project risk is the:
Contract
Specification
Statement of work
Work peakdown structure
Network programming diagram
对一个项目,假定的风险值最好是通过一个结构的方法论来完成以便所有项目的因素都被评估. 用于项目风险的结构分析的最合适的工具是:
合同
规范
工作描述
工作分解结构
网络规划图
6. The total amount of risk that is calculated for a project is found by:
Multiplying the sum of each the risks times the amount at stake
Calculating the cumulative sum of the probability for each risk and multiplying this value times the consequence of occurrence of the risk events
Cannot be calculated since all risks are not known
The amount of project reserves available
通过那一种手段来计算项目风险的总量:
每个风险的总和乘以风险的价值量
计算每个风险的可能性累计总和同时转换成价值乘以风险事件发生的频率
由于所有风险不确定不能计算
项目的可用的储备金
7. Bo calls his project team to quantify and assess the risks of their project. The benefits the team will gain from this exercise include all but which of the following?
Thoroughly understand the project, the associated risks and the impact of risk on all parts of the project
Develop risk mitigation strategies for dealing with issues identified
Ensure all identified risk issues are incorporated into project planning
Identify alternatives which may exist
玻叫他们的项目组把项目的风险量化和评估. 哪一相不是项目组从这一活动中得到的?
彻底地了解项目,相关的风险和项目所有部分的风险的影响
进一步发展缓解风险策略以处理已经确认的问题
保证所有已经确认的风险都被统一的考虑在项目的计划中
确认那一个可能存在的选择方案
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1学校工程施工现场平面布置图
- 2安全工程师考试《安全生产管理》第一讲讲义精选(1)
- 32015年咨询工程师《工程咨询概论》每日一练9.18
- 42015年咨询工程师每日一练免费在线测试(2015.5.29)
- 5《宏观经济政策与发展规划》知识点:产业结构调整的目标
- 62015年招标师《专业实务》辅导:工程建设项目设计管理特征
- 7脚手架的拆卸必须符合的安全要求
- 82015年湛江市安全工程师考试报名截止时间为6月21日
- 9资金时间价值及习题
- 102015年咨询工程师《工程项目组织与管理》每日一练汇总2.25-3.3
- 11平板机安全要求
- 122015造价员《土建工程》基础知识点:强夯工程
- 13项目材料、机械设备、工程技术人员的管理责任内容
- 14造价工程师考试辅导:成本与费用的估算(1)
- 152015招标师考试项目管理考点:货物生产供应链
- 162013年四川二级建造师变更注册申请表
- 1724米跨双线简支箱型梁制造施工工法
- 182015招标师考试项目管理考点:招标采购项目计划的编制
- 19武黄城际铁路施工有条不紊 黄石北站八月份竣工
- 202011年PMP考试试题分布更新通知
- 21国家能源局:禁建年产20亿方以下煤制气项目
- 222015安全工程师《安全生产法及法律知识》巩固练习(2)
- 232015年咨询工程师:投资估算的范围与内容
- 24大厦工程施工现场平面布置图(基础、结构、装修)
- 252015年造价工程师考试辅导:工程寿命周期成本
- 262015年咨询工程师《工程咨询概论》考试模拟试题(8)
- 27成绵乐客专铺轨完成60% 预计年底通车
- 282015年富阳市造价工程师考试报名时间为6月16日至30日
- 292015年咨询工程师《组织与管理》每日一练(4.19)
- 30《招标采购法律法规与政策》第三章:对备选方案的处理办法
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼