PMP认证考试练习题及参考答案(五十一)
A Developing system (policies, procedures, responsibilities)
B Obtaining insurance against loss
C performing contingent planning
D developing planning alternatives
E identification of project risks.
ans:E
2 Deflection involves the transfer of risk by:
A Contracting out to another party
B Developing schedule alternative.
C Establishing functions under the project manager to handle risk events.
D Disaster planning and responses.
E None of the above.
ans:A
3 The formalization of management's attitude toward risk is called _____ .
A Decision Theory.
B Utility Theory.
C Decision Tree Analysis.
D Sensitivity Analysis.
E Probability Analysis.
ans:B
4 Risks that cannot be identified or evaluated _____ .
A should be deflected to the contracting officer.
B should be handled via contingency allowances.
C should be ignored, since they cannot be identified.
D should be ignored, since they are not covered in the Risk Assessment.
E C and D
ans:B
5 Range estimating in determining cost risk probabilities requires _____ .
A an amount of financial exposure.
B risks and opportunities ranked in order of bottom line importance
C contingency requirements for expected level of confidence
D probability of cost overrun occurrences
E All of the above.
ans:E
6 Standard deviation of project completion is _____ .
A a relationship of the uncertainty of critical path activities. www.Examda.CoM
B an indicator of project end date target confidence
C a function of critical path, leveling and project costs.
D A and B
E All of the above.
ans:D
7 Which of the following does not contribute to increased Schedule Risk?
A labor shortage
B contractor claims
C lack of access
D sponsor scope changes
E all may increase schedule risk
ans:E
8 Screening of risk events for potential risk is known as _____ .
A problem structuring.
B risk identification
C risk quantification
D risk modeling
E risk mitigation
ans:B
9 The schedule risk is the _____ .
A the accumulated "expected' durations which maintain project completion.
B Critical Path adjusted by "high-risk" activity float.
C highest risk path that maintains quality.
D Critical Path when calculated with "most likely" duration.
E highest risk path that contributes the most risk toward the project completion.
ans:B
10 Pure Risk differs from Business Risks because Pure Risk's _____ .
A include chances of both profit or loss associated with the business.
B include chances of loss and no chances for profit associated with the business.
C must incur personal loss with business liability.
D must incur business liability associated with loss of pure profit.
E B and C
ans:B
11 Response Planning is the responsibility of the functional areas and considers
A mitigation.
B deflection.
C contingency planning.
D unforeseen occurrences.
E All of the above.
ans:E
12 Amount at Stake is the _____ .
A function of planned time/real time project costs.
B risk identified in successful project completions.
C (Standard Project Deviation + Expected Costs)/6
D cost of investment loss + least cost to restore status quo.
E inherent risk at conception altered by standard project deviations.
ans:D
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1某工程消防报警及自动灭火系统施工方案29P
- 2抹灰工程施工过程质量检查要点
- 3工程管理软件开发工具
- 4监理工程师考试2015年《工程合同管理》习题(8)
- 5PMP认证考试练习题(一)(中英文)
- 6【学员心声】监理考试高分学员是什么样的
- 7园林绿化、小品、电气安装工程施工
- 82015招标师考试:招标采购专业实务详解44
- 9塑料排水板专项施工方案
- 102012一级建造师《公路工程》:工程价款主要结算方式的比较
- 11某文化广场景观工程施工组织设计13p
- 122015年咨询工程师《工程项目组织与管理》每日一练(9.24)
- 13安全工程师安全生产技术复习要点:锅炉严重缺水的处理方法
- 14湿陷性黄土用挤密法
- 15EPS聚苯板外墙外保温施工工艺
- 16长沙检验检疫局协助湖南省开辟工程机械出口新领域
- 172015二级建造师《施工管理》掌握关键工作和关键路线的概念
- 18福建某医院病房综合楼地下室防水施工方案
- 19田桓铁路将于4月18日正式破土动工
- 20狭长形基坑开挖应符合的规定
- 21水泥搅拌车养护中要留意哪些问题?
- 22在搅拌车保养中有哪些是只要保养的项目?
- 23某大型企业施工组织设计编制大纲
- 242015年造价工程师(安装)知识精讲(8)
- 252015一级建造师《市政工程》讲义摘要(7)
- 262015年安全工程师《安全生产技术》每日一练(1.31)
- 27造价工程师土建计量复习要点:钢筋弯曲机、切割机、调直机
- 28搅拌车保养错误维护方式
- 29安全工程师法规复习要点:城乡规划
- 30PMP认证考试练习题及参考答案(二十六)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼