PMP认证考试练习题及参考答案(三十七)
A Control charts can be used to establish as well as maintain process control
B control charts are used to detemine acceptance limits when no limits are stipulated by the product specification; otherwise, one should use the limits dictated by the specification.
C all data points outside the control chart limits are variations explained by assignable causes.
D A and B. 来源:考试大
E B and C
ans:E
2 A quality control manager decides to increase his daily sample size from three to six. The size of the control band will:
A increase
B decrease
C remain unchanged
D not determinable from given data
E None of the above.
ans:B
3 All of the following statements about acceptance sampling are true except:
A Acceptance sampling plans are beneficial when the cost of inspection is high and the resulting loss of passing nonconforming units is not great.
B Acceptance sampling plans are necessary when destructive inspections are required.
C Acceptance sampling plans are never effective at rejecting nonconforming units as 100 percent inspection, even when the inspection process is very tedious.
D Acceptance sampling plans do not directly control the quality of a series of lots; they instead specify the risk of accepting lots of given quality.
E Acceptance sampling plans are not very effective for inspecting small lots of custom-made products.
ans:C
4 In acceptance sampling, if the sample size is kept the same but the acceptance number is increased, which of the following will be true:
A buyer's risk will decrease
B vendor's risk will decrease
C producer's risk will decrease
D consumer's risk will increase
E C and D only
ans:E
5 The risk of accepting a lot of poor quality, in acceptance sampling, is referred to as:
A buyer's risk
B consumer's risk
C producer's risk
D type I error
E B and D only
ans:B
6 Standard "Shewhart" control charts assume that the distribution of sample means is:
A uniform
B normal 来源:考试大网
C discrete
D symmetrical
E B and D only
ans:E
7 The specification for a particular part is 10" + or - 0.015". The standard associated process produces parts with a means of 10" and standard deviation of 0.002'. The process capability index is:
A 0.002
B 1
C 2.5
D 7.5
E None of the above
ans:C
8 Random cause or system variation is:
A generally present in every process
B the responsibility of the inspection of the process
C the responsibility of the workers of the process
D the responsibility of management
E A and D only
ans:E
9 The centerline of a standard "Shewhart' control chart represents:
A the process target
B the nominal dimension specified by the customer
C the nominal dimension specified by the designer
D the true process average or mean
E the process sample average or mean
ans:E
10 100 % inspection of output is:
A the best proven method to ensure quality
B is expensive, ineffective approach to quality management
C can never be, justified
D can still leave some defects undetected 来源:www.examda.com
E B and D only
ans:E
11 Quality control charts show a characteristic of the product or service against:
A the specification limits
B customer requirements
C control limits based on three standard deviations in each direction
D control limits based on six standard deviations in each direction
E A and D only
ans:C
12 Variables quality data are:
A quantitative or qualitative data
B quality data for which the product or service is designed and built
C reflect measurements on a continuous scale of a characteristic of the produce or service.
D Indicate management's understanding of the concept of variability
E B and C only
ans:E
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1影响边坡稳定性有哪些主要因素?
- 2宿迁考试鉴定网公布2015年安全工程师执业资格考试报名通知
- 3[北京]通州区一工地升降机从15层坠落 工人当场身亡
- 4粘贴钢板加固工艺流程及施工方法
- 52015造价工程师考试《理论与法规》课程讲义(17)
- 6防搅拌车积碳的小窍门
- 72015年咨询工程师《政策与规划》每日一练(5.13)
- 8中铁七局延延高速公路LJ-7标项目部主体工程顺利完工
- 92015年造价工程师考试辅导:合同的形式
- 10我国核电建设重启 华能称石岛湾核电站本周开工
- 11竞争性谈判“不足三家” 如何谈?
- 12【重要提示】2015年重庆安全工程师考后资格审核相关事宜
- 13安全工程师答疑精华:龛灯
- 14斗轮机施工措施
- 15 [陕西]酒店工程施工现场平面布置图、临建图、临水图、临电图
- 16建筑施工安全一般要求有哪些
- 17基坑工程施工过程中的监测
- 18安全工程师考试《安全生产技术》重点题目(十五)
- 19振冲挤密法(基底处理)施工
- 20吉图珲客专飞跨图们江
- 21通过监理工程师考试的12个复习技巧
- 22 2015年二级建造师《法规及相关知识》每日一练(9.6)
- 23《项目管理与招标采购》辅导:工程保险
- 24搭设纵、横向水平杆的注意事项
- 25安全工程师考试《安全生产技术》重点题目(二十四)
- 26地下水的类型及其埋藏条件是什么?
- 272013年二级建造师《法规及相关知识》每日一练(12.25)
- 28农村公路土方路基的施工方法
- 29赣粤高速公路某隧道实施性施工组织设计
- 30安全工程师考试《安全生产管理》第五讲讲义精选(1)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼