PMP认证考试练习题及参考答案(三十六)
A Capital budgeting process.
B Overhead rates.
C Contracts and administration costing system.
D Fringe benefits packages.
E None of the above. www.Examda.CoM
ans:B
2 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.
A Increase, increase.
B Increase, decrease.
C Decrease, decrease.
D Decrease, increase.
E Remain the same, return to customer.
ans:E
3 The most effective means of determining the cost of a project is to price out the _____.
A Work breakdown structure.
B Linear responsibility chart. 来源:考试大
C Project charter.
D Scope statement.
E Management plan.
ans:A
4 The most expensive phase of life cycle costing is:
A R & D.
B Applied research.
C Production
D Operations and support.
E Termination.
ans:D
5 A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
A Parametric
B Definitive.
C Budget
D Bottom up.
E Top down.
ans:C
6 The most precise or accurate estimate for determining project costs is the _____ estimate.
A Definitive.
B Analogy
C Budget
D Modified standards.
E Rule of thumb.
ans:A
7 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.
A Definitive, bottom up.
B Analogy, top down.
C Parametric, bottom up.
D Parametric, top down. www.Examda.CoM
E Analogy, bottom up.
ans:D
8 A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.
A Inventory control.
B Materials management.
C Procurement.
D All of the above.
E A and C only.
ans:B
9 There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.
A Management reserve, unplanned allowance fund.
B Management reserve, contingency.
C Contingency fund, management reserve.
D Unplanned allowance fund, budgetary reserve.
E Unplanned reserve, planned reserve.
ans:C
10 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:
A Overhead rates, labor rates and material costs.
B Overhead rates, schedule slippages, and rework.
C Rework, cost-of-living adjustments, and overtime.
D Material costs, shipping cost, and scope changes.
E Labor rates, material costs, and cost reporting.
ans:A
11 The three most common types of project cost estimates are:
A Order of magnitude, parametric, and budget.
B Parametric, definitive and top down.
C Order of magnitude, definitive and bottom up.
D Order of magnitude, budget and definitive.
E Analogy, parametric and top down.
ans:D
12 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:
A Code of accounts.
B Overhead rates.
C Budgeting system.
D Capital budgeting process.
E All of the above.
ans:A
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1《宏观经济政策与发展规划》知识点:我国重点产业的确定
- 22015年招标师考试招标采购专业实务考前复习指导(91)
- 3合同洽谈与沟通
- 42015年安全工程师安全生产管理知识模拟题(6)
- 5造价工程师造价案例分析复习要点:延尺系数
- 6城市热力管道工程管道安装及检验的施工要求
- 7湖南机械为您介绍混凝土输送泵管道如何架设
- 8搅拌车底盘养护注意事项
- 9项目员工教育培养 内容
- 103某工程园林工程技术标书
- 112015年一级建造师《工程经济》第一篇冲刺讲义(1)
- 12安徽注册消防工程师资格考试辅导教材征订
- 13规范招标文件编写(上)
- 14储秀斌:贫困县形象工程 见怪不怪
- 152013年内蒙古二级建造师注册证书、执业印章遗失补办申请表
- 16惊吓!越南羽毛球公开赛现场 体育馆房顶突然坍塌
- 172015年咨询工程师《工程项目组织与管理》每日一练(1.11)
- 182015年安全工程师考试《管理知识》模拟题(39)
- 19[开封]07造价工程师考试6.11起报名
- 202015年招标师《项目管理与招标采购》练习及答案7
- 21造价工程师技术与计量复习要点:相应脚手架
- 22某立交桥钢箱梁液压提升安装施工
- 23安全工程师生产技术复习要点:传送带
- 24强夯法加固机理有哪些要求?
- 25工程造价基础:开标、评标与定标
- 26[广州]大型工程施工进度计划、资源需求计划
- 272015年福州安全工程师报名时间
- 28中铁电气化局西格二线关角隧道首台箱变一次送电成功
- 29交通运输安全技术模拟试题及参考答案
- 302012一级建造师《公路工程》:中心站集中拌合法施工
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼