PMP认证考试练习题及参考答案(二十九)
1 Which of the following impacts the critical path?
A Changing the task duration.
B Reduce the free float of an activity.
C Executing a backward pass
D A or B
E None of the above.
ans:A
2 The range of time allowed for an activity to be completed in is the _____.
A Planned time (Duration).
B Float time (LS - ES, or LF - EF).
C Critical time (when ES = LS, or EF = LF). 来源:www.examda.com
D Scheduled time (LF - ES).
E Event.
ans:D
3 Free float is the amount of time that an activity may be delayed with out affecting the _____.
A Early start of the succeeding activities.
B Late start of the succeeding activities.
C Project finish.
D Cost of the project.
E None of the above.
ans:A
4 Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.
A 0.5
B 1
C 1.8
D 2.2
E 2.8
ans:C
5 In crashing a task, you would focus on:
A As many tasks as possible.
B Non critical tasks. http://ks.examda.com
C Accelerating performance of tasks on critical path.
D Accelerate performance by minimizing cost.
E A and D.
ans:C
6 Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task
A 8
B 8.8
C 9.1
D 9.7
E 10.5
ans:B
7 Using the WBS in the Special window, an instance of a work package is:
A Build house
B Excavate
C Prepare Foundation
D B and C
E None of the above 来源:考试大网
ans:E
8 All of the following are categories of a milestone in a schedule except:
A End date.
B Contract dates.
C Key events scheduled.
D Imposed dates.
E Task duration.
ans:E
9 The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A Increases.
B Is not affected by
C Does not require
D Is heavily dependent upon
E Is the only means of determining
ans:D
10 Excessive flexibility in specifying requirements will _____ the likelihood of time overruns.
A Reduce.
B Eliminate.
C Double
D Increase
E Not affect
ans:D
11 The key purpose of project control is to:
A Plan ahead for uncertainties.
B Generate status reports.
C Keep the project on track.
D Develop the project road map.
E All of the above. 来源:考试大网
ans:C
12 Fast tracking means to:
A Speed up a project through parallel tasks.
B Swap one task for another.
C Reduce the number of tasks if possible.
D B and C.
E None of the above.
ans:A
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1招标师职业水平考试:项目管理与招标采购第二章练习题35
- 22013年陕西二级建造师增项注册申请表
- 310种心态助你顺利通过2015年二级建造师考试
- 4西安危房改造将使6000农户圆“安居梦”
- 5二建复习资料基坑支护结构变形监测
- 6搅拌车向右跑偏是怎么回事?
- 7对搅拌车激烈加油、频繁刹车的弊端
- 8【任性备考】网校名师真优秀 一次通过二建有保障
- 92015安全工程师《生产管理知识》试题精选(12)
- 10城市桥梁工程施工方案的内容
- 11造价工程师复习资料:各级编码的代码含义
- 122015监理工程师考试《工程质量与进度控制》模拟题(1)
- 13近两年全国至少有32家上市宣布进军养老地产项目
- 142015年招标师考试《管理与采购》复习材料(1)
- 15房地产腐败窝案:一楼盘击倒40多名干部 涉案金
- 16惠州市2015年造价工程师考试报名时间为6月8日-7月2日
- 17曲阜市强力推进小城镇建设
- 182015年咨询工程师《工程项目组织与管理》每日一练(3.21)
- 19强夯处理湿陷性黄土施工工法
- 20我国首座工程机械馆长沙落成
- 21住宅产业化发展问题及对策
- 222015年安全工程师《管理知识》:职业病报告内容
- 232015年招标师考试《案例分析》考前提高试题1
- 24金温铁路全线跨度最大隧道下岙一号隧道顺利贯通
- 25某工程水暖系统施工组织设计 64p
- 26建筑工程现场施工经验——钢筋绑扎的部分基础知识(19)
- 27[浙江]隧道工程施工组织设计
- 282015年监理工程师考试《建设工程合同管理》习题(20)
- 292015年咨询工程师《工程咨询概论》考前练习题(10)
- 302015年安全工程师《生产技术》:矿(地)压的基本概念
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼