PMP认证考试练习题及参考答案(二十八)
1 A task-oriented family tree of activities is a:
A Detailed plan.
B Linear responsibility chart.
C Work breakdown structure.
D Cost account coding system.
E Work package description.
ans:C
2 Management plans include all of the following except:
A Organization of project.
B Job descriptions.
C Policies and procedures.
D Linear responsibility charts. http://ks.examda.com
E Scope baseline.
ans:E
3 A comprehensive definition of scope management would be:
A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
B Approval of the scope baseline.
C Approval of the detailed project charter.
D Configuration control.
E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
ans:A
4 The process of choosing/documenting the best approach to achieve the project objectives is part of:
A The scope baseline.
B Scope authorization
C Scope definition 来源:考试大
D Scope planning.
E All of the above.
ans:D
5 A completion of a local government study resides on your critical path. This would most likely be referred to as:
A Soft logic
B Hard logic
C An external dependency
D A mandatory dependency
E A lost cause
ans:C
6 Which of the following can affect network durations?
A Skills of the resource pool
B Calendar dates
C Constraints
D All of the above
E A and B only
ans:E
7 Sources for data on activity durations and resource requirements can be gathered from which of the following:
A Past project records (historical data)
B Commercial techniques (standard practices, rules of thumb)
C Past project team members knowledge (experience, oldtimers)
D All of the above www.Examda.CoM
E A and C only
ans:D
8 The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency.
A Discretionary
B Mandatory
C External
D Soft logic
E Subcontracted
ans:B
9 "Hard logic" in the preparation of a network refers to:
A Discretionay dependencies
B External depenencies
C Mandatory dependencies
D All of the above
E A abd B only
ans:C
10 The difference between a project and a program is that:
A A program is made up of multiple projects
B A program requires at least three times longer to plan than a project
C A project is a one-shot deal while a program is on-going
D A and C
E B and C
ans:D
11 As a control tool, the bar chart (Gantt) methods is most beneficial for:
A rearranging conflicting tasks
B depicting actual versus planned tasks
C showing the outer dependencies of tasks
D A and C.
E A and D
ans:B
12 You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks. You should:
A Immediately inform the sponsor and ask for advice
B Do nothing until the slippage occurs
C See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis
D Look for someone to blame before you see the sponsor
E Inform your senior management of the problem and tell them that you will get back to them after you assessed the situation
ans:C
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1涨壳式中空锚杆注浆锚杆的施工方法
- 22015年咨询工程师《工程咨询概论》每日一练(2.15)
- 3IDL外墙外保温体系施工工艺
- 42015年招标师考试:招标实务问答(100)
- 5某市保障性住房工程勘察设计阶段监理规划
- 62015年安全工程师《安全生产法及相关法律知识》每日一练(4.21)
- 7中铁十六局五公司成贵项目部桥梁桩基突破800根
- 82015年咨询工程师《工程咨询概论》考试模拟试题(1)
- 9喷泉施工方法
- 10安全工程师答疑精华:TN-C-s系统
- 11安全工程师答疑精华:调查组
- 12项目组织与管理考点:工程项目范围管理
- 13南广铁路首个站改工程竣工通车
- 142015年安全工程师考试《安全生产法》:监督管理部门
- 15砺志PMP模拟题每周精选2
- 162015年咨询工程师《宏观经济政策与发展规划》每日一练6.24
- 17日本园林的植物景观与植物应用Japanese Landscape and hortuculture
- 182015.4.9咨询工程师每日一练免费在线测试
- 192015年果洛造价工程师报名时间为7月2日-11日
- 202015年监理工程师《建设工程合同管理》习题(15)
- 212015年咨询工程师《组织与管理》每日一练(6.5)
- 222015安全工程师《安全生产法及法律知识》试题(4)
- 23大厦消防设计
- 24世界贸易组织《政府采购协议》的主要内容
- 25某小区道路及排水工程施工组织设计53P
- 26预应力混凝土连续梁悬臂浇筑挂篮施工工法
- 27安全工程师相关法律知识点:安全生产社会监督、舆论监督
- 282015年注册安全工程师事故案例分析模拟试题(二十)
- 29夏威夷“阳光小岛”豪华古典卡帕鲁尼丽思卡尔
- 30施工项目质量检验程度 主要内容
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼