1. which of the following fall(s) under the responsibilities of a project manager?
a. labor relations with project personnel
b. affirmative action
c. personnel training
d. discrimination and equal employment opportunity
e. all of the above
ans: e
2. a legally binding document offered unilaterally is a _____ .
a. purchase order
b. scope of work description
c. contract stipulation
d. level of effort proposal
e. request for proposal考试大论坛
ans: a
3. a technical requirement has which of the following characteristics:
a. easy to understand
b. a communication tool between the user and the design team
c. written in non-technical language
d. developed in cooperation with the user
e. typically describe physical dimensions and performance requirements
ans: e
4. if a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project
manager should assume:
a. the message was understood
b. the message was not understood
c. the subordinate discarded the information
d. the information was not appropriate
e. none of the above.
ans: e
5. inspection of a complex project according to specifications is accomplished by _____.
a. inspection by attributes.
b. cyclical inspection
c. quality conformance inspection
d. original inspection来源:考试大网
e. none of the above.
ans: c
6. the behavioral responsibilities of a project manager may also include dealing with:
a. the public
b. regulatory personnel
c. the legal environment
d. environmental issues
e. all of the above
ans: e
7. the difference between the bcws and the bcwp is referred to as the:
a. schedule variance
b. cost variance.
c. estimate of completion
d. actual cost of the work performed
e. none of the above
ans: a
8. "paraphrasing" is most closely associated with which part of the communication process?
a. encoding
b. decoding
c. barriers
d. feedback
e. none of the above.
ans: d
9. a gantt chart is useful in determining:
a. the level of effort for a task
b. when a task starts and stops
c. how tasks are related to each other
d. who is assigned to do a task来源:考试大
e. all of the above.
ans: b
10. a contract originated bilaterally may be developed by _____ .
a. quotation request from suppliers
b. proposal request
c. bid invitation release
d. b and c
e. all of the above.
ans: e
11. in a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance
review?
a. not working directly with the assigned functional employees
b. employees spend only a short amount of time assigned to the project
c. not being knowledgeable enough to evaluate employees on technical judgment
d. all of the above
e. a and b only
ans: d来源:www.examda.com
12. upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are
referred to as the:
a. baseline costs
b. budgeted costs.
c. estimates upon completion costs
d. scheduled costs
e. none of the above
ans: a
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1浙江省2015年安全工程师考试报名时间为4月14日至28日
- 22015年招标师考试招标采购专业实务考前复习指导(42)
- 3PMP认证考试练习题及参考答案(四十)
- 42015年咨询工程师《项目决策分析与评价》每日一练(5.18)
- 52015年咨询工程师《咨询方法与实务》模拟试题(52)
- 6工艺管道、吹扫、清洗施工方案
- 72015安全工程师《相关法律知识》:烟花爆竹燃放规定
- 8如何从搅拌车方向盘上辨故障?
- 9一级建造师建筑工程复习要点:工程质量事故的处理程序
- 10电网建设再投22亿 相关产业将受益
- 112015年咨询工程师《宏观经济政策与发展规划》每日一练(3.19)
- 12金温铁路扩能改造工程:青田段已完成总工程量88%
- 13地下建筑顶层加固立塔施工新技术
- 142015年监理工程师《建设工程合同管理》练习题(25)
- 15园路工程课件 园路铺装
- 162015造价员《土建工程》基础知识点:建设单位管理费
- 172015年一级建造师《项目管理》精华知识点(18)
- 182015年招标师考试:招标项目计划管理应具备什么条件?
- 19在代理型CM模式下,CM合同价格为什么
- 20拖管工艺
- 21竖向承载力与沉降有哪些群桩效应?
- 22平度市2015年造价工程师考试报名时间为5月19日至6月2日
- 23[宁夏]06年造价师考试6.12-23日补报名
- 24造价工程师案例分析复习要点:调整所得税计算基数问题
- 25招标师考试《案例分析》考前提高试题汇总
- 26高铁绿化工程施工技术交底10p
- 27济南市2015年安全工程师考试报名时间为6月下旬至7月上旬
- 282012一级建造师《公路工程》:现场材料管理的作用
- 292015造价员《土建工程》知识点:溶剂型合成树脂涂料
- 30注册咨询工程师2015年《项目决策分析》习题(14)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼