PMP认证考试练习题及参考答案(十七)
1. you must produce 27 widgets. you can only produce 9 widgets per production run. each production line setup costs $1000. each widget
consumes $10 worth of material and $5 worth of labor. what is total variable cost for producing one widget.
a. 1020
b. 1010
c. 1015考试大论坛
d. 20
e. none of the above
ans: e
2. creation of project objectives:
a. allows for data collection and analysis and progress reporting against which standards of performance can be measured.
b. is accomplished by selection of measurable variables against which performance can be judged.
c. is required before funding of the project by the project sponsor.
d. all of the above.
e. a and b only
ans: e
3. during which phase of the project life cycle is the amount at stake lowest?
a. concept
b. development
c. execution
d. conclusion来源:www.examda.com
e. c and d
ans: a
4. techniques that can improve communication include:
a. establishing a single, one-way communications channel
b. avoiding face-to-face communication
c. using redundancy (i.e. saying it two different ways) whenever possible
d. disregarding the sensitivity of your receiver
e. all of the above.
ans: c
5. the delphi method is well-suited for:
a. decision-making
b. forecasting
c. overhead rate estimating
d. all of the above
e. a and b only
ans: e
6. the zero defects concept
a. is a performance standard for management
b. is a motivational technique that promotes "doing it right the first time".
c. is used by management to communicate to all employees that everyone should do things right the first time.
d. a and c.
e. b and c来源:考试大
ans: d
7. what tool have project managers come to use to identify all of the costs associated with a project.
a. a bill of materials
b. a gantt chart
c. an arrow diagram network.
d. a work breakdown structure.
e. b and c only.
ans: d
8. _____ is a receipt issued by a carrier for merchandise to be delivered to a party at some destination.
a. proforma invoice
b. inspection certificate
c. packing list
d. bill of lading
e. none of the above.
ans: d
9. a program is characterized as:
a. a grouping or related tasks lasting one year or less.
b. a unique undertaking having a definite time period.
c. a grouping of similar projects having no definite end that supports the product(s) from cradle to grave.
d. a project with a cost over $1 million.来源:考试大
e. none of the above.
ans: c
10. contingency planning should include all but which of the following?
a. the development of a contingency allowance determined by combining (layering) various estimate segments to form larger estimate segments.
b. the development of schedule alternatives and work-around
c. the management of a contingency budget
d. an assessment of project shut-down liabilities.
e. a and c
ans: a
11. from an operating or functional perspective, there are various objectives of purchasing and materials management. which is not one of these
objectives?
a. to buy competitively
b. to support company operations with an uninterrupted flow of materials and services
c. to develop reliable and effective sources of supply
d. to achieve maximum integration with the other departments of the firm
e. to attain approval from each department of every purchase
ans: e
12. in order to achieve long-term quality improvements, management must do the following:
a. motivate the employees with seminars, contests, and institute programs such as "quality improvement' day.
b. create a quality control department and give the head of the department ultimate responsibility for quality improvement.
c. implement of a formal quality control program with worker and management involvement.
d. establish financial incentive packages for worker.
e. a and d
ans: c
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1选购原木门技巧
- 2一级建造师工程经济复习要点:递延所得税负债
- 32015招标师法规与政策考前知识点:机电产品国际招标项目
- 4上航局连中连云港两工程项目
- 52015年咨询工程师知识点:具体项目论证
- 62015年二级建造师《建筑》:绑扎脚手架
- 72015年招标师《专业实务》辅导:货物采购分标
- 8采购合同的审批权限 内容
- 9宏观经济政策与发展规划考点:规范政府核准制
- 10《工程项目组织与管理》:工作定义的依据
- 11合肥房屋靠太阳降温 这不科学?
- 12[云南省]2005造价工程师5月9至5月27报名
- 13[福建]政府强拆"钉子户" 称其漫天要价影响工期
- 14经济政策与发展规划知识点:新型工业化的特征
- 152015年安全工程师考试《安全生产法及相关》练习题(26)
- 162015年天津注册消防工程师报名时间
- 17贵州森林公园改建高尔夫球场 曾被要求停工未果
- 18[上海]06年度造价师考试合格人员填表要求
- 192015年招标师法律法规政策考试练习题(15)
- 20安全工程师生产法复习资料——烟花爆竹安全生产标准体系
- 21全国监理工程师2015年考试《合同管理》习题(8)
- 22中国境内的主要地震带
- 23项目决策分析与评价知识点:选址原则及注意事项
- 24《项目管理与招标采购》考前提高试题12
- 252015年招标师法律法规高频考点:评标委员会的组成
- 262015.4.15咨询工程师每日一练免费在线测试
- 272015年咨询工程师《工程咨询概论》每日一练3.19
- 28如何检查搅拌车的火花塞?
- 29江苏连云港市开发区借鉴PMC模式控制造价
- 30项目管理与招标采购第二章:工程建设项目合同管理的重要性
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼