PMP认证考试练习题及参考答案(三十二)
A Reveals interdependencies.
B Facilitates "what if" exercises.
C Highlights critical activities.
D Provides information on resource requirements, time requirements and tradeoffs.
E All of the above.
ans:E
2 The major disadvantage of a bar chart is:
A Lack of time-phasing.
B Cannot be related to calendar dates.
C does not show activity interrelationships. 来源:考试大
D Cannot be related to manpower planning.
E Cannot be related to cost estimates.
ans:C
3 The most common types of schedules are Gantt charts, milestone charts, line of balance, and:
A Networks.
B Time phased events.
C Calendar integrated activities.
D A and C only.
E B and C only.
ans:A
4 Scheduling is the process by which decisions are made concerning:
A Tasks to be accomplished.
B Personnel/organization that will be assigned to accomplish the task.
C Time when the tasks are to be completed.
D All of the above.
E A and C only.
ans:E
5 Time management is the allocation of time in a project's life cycle through the process of:
A Planning
B Estimating.
C Scheduling.
D Controlling 考试大(www.Examda。com)
E All of the above.
ans:E
6 Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:
A $19K
B $21K
C $26K
D $29K
E indeterminate
ans:C
7 Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A Become worse, become worse
B Become worse, improved
C Improved, increased
D Improved, become worse
E None of the above are correct
ans:B
8 The computation for Cost Performance Index is:
A BCWP/ACWP
B BCWP-ACWP 来源:www.examda.com
C BCWP-BCWS
D ACWP/BCWP
E ACWP-BCWS
ans:A
9 When comparing the cost of competing projects, which of the following is typically NOT considered?
A Opportunity costs.
B Direct costs.
C Sunk costs.
D Indirect costs.
E Burden rates.
ans:C
10 The Cost Performance Index (CPI) measures:
A cost of work performed vs planned costs.
B work performed vs cost of work performed.
C work performed vs planned work.
D direct costs vs indirect costs.
E floating costs vs. sunk costs.
ans:B
11 Parametric estimates are based on variables such as:
A Detailed planning and cost restraints.
B Physical characteristics and historical data.
C The WBS and similar projects. 来源:www.examda.com
D Project objectives and manpower allocations.
E Precise measurements and multiple inputs.
ans:B
12 Cost and schedule data are usually integrated because:
A optimized project cash flow can affect financial requirements
B they provide MIS with an integrated system to produce reports
C they control escalation allowances
D they account for omissions in the definitive estimate
E they predict future performance
ans:E
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015一级建造师《法规及相关知识》冲刺指导(10)
- 2压力容器焊接接头设计
- 32015年造价工程师考试《理论与法规》课程讲义(12)
- 4IPMP申请:IPMP认证费
- 5工程咨询概论考点:投资的定义与分类
- 62015年武威造价工程师报名入口
- 7工程造价精华50条(一)
- 82015招标师考试项目管理考点:变更与洽商
- 92015招标师考试教材:合同的订立与效力
- 10滨绥线牡丹江至绥芬河段扩能改造工程某隧道(实施)施工组织设计
- 11农迁房工程给水管网安装施工组织设计50p
- 12造价工程师建设工程计价复习资料——我国与世界银行的合作
- 13一级建造师管理与实务复习要点:正反循环钻孔
- 14搅拌车发动机常见的故障原因分析
- 152015年监理工程师考试理论与法规练习题(58)
- 16名师达江解答二级建造师相关疑问——报名篇(六)
- 172012一级建造师《建筑工程》:地基基础常见质量通病
- 182015年咨询工程师《工程咨询概论》每日一练4.7
- 19山东烟台西港区亿吨大港 欲建世界最大码头
- 202015年招标师考试《招标采购案例分析》模拟试题(4)
- 212015年招标师考试《法律法规与政策》复习资料:第一章9
- 22中铁建工集团有限公司公开招聘公告
- 23某工程园林绿化施工组织设计
- 24咨询工程师《宏观经济政策与发展规划》自测题(32)
- 252006年度全国监理工程师资格考试建设工程监理基本理论与相关法规试卷及答案
- 262015年一级建造师《工程经济》第三篇冲刺讲义(5)
- 27某职工宿舍楼工程施工进度计划网络图(CAD版)
- 28西安某工程完整周期建设方进度计划
- 292015年一级建造师《公路工程》路面工程施工(2)
- 30世界贸易组织《政府采购协议》的主要内容
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼