PMP认证考试练习题及参考答案(二十三)
1 Work packages are used to:
A Represent units of work at a level where work is performed.
B Clearly distinguish one work package from all others assigned to a single functional group.
C Limit the work to be performed to relatively short periods of time.
D All of the above. 考试大论坛
E A and B only
ans:D
2 Project life cycles are very useful for _____ and _____ .
A Configuration management, termination
B Objective setting, information gathering
C Standardization, control
D Configuration management, weekly status updates
E Approval, termination
ans:C
3 Which of the following are included as part of a scope statement?
A Project justification
B Project deliverables
C Project objectives
D All of the above
E B and C
ans:D
4 The initial document that formally recognizes the existence of a project is the _____ .
A Scope baseline
B Management plan 来源:www.examda.com
C Project charter
D Configuration control report
E None of the above
ans:C
5 Which of the following is not a scope management process?
A Initiation
B Scope planning
C Scope Definition
D Scope change control
E Scope verification
ans:D
6 In which of the following scope management processes is the scope management plan prepared?
A Initiation
B Scope planning
C Scope Definition
D Scope change control
E Scope verification
ans:B
7 The project charter is prepared in which scope management process?
A Initiation
B Scope planning 考试大论坛
C Scope Definition
D Scope change control
E Scope verification
ans:A
8 The work breakdown structure (WBS) is first developed in which scope management process?
A Initiation
B Scope planning
C Scope change control
D Scope Definition
E Scope verification
ans:D
9 In which of the following scope management processes are subject matter experts used?
A Initiation
B Scope planning 来源:www.examda.com
C Scope Definition
D Scope change control
E Scope verification
ans:A
10 A Work Berakdown Structure is most useful for:
A Identifying individual tasks for a project.
B Scheduling the start of tasks.
C Developing a cost estimate.
D Determining potential delays.
E A and C.
ans:E
11 The scope statement provides
A A basis for future decisions about a project.
B A baseline to accomplish verification measures.
C A baseline to evaluate potential scope changes.
D All of the above
E B and C only
ans:D
12 A work breakdown structure:
A assures all work is identified.
B subdivides the project into manageable segments.
C provides the project sponsor with a time-phase task summary.
D both A and B.
E All of the above.
ans:D
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1项目达到了质量目标,但用户的质量调查结果却很差
- 2安全工程师电工安全技术考核试卷(B卷)
- 3挖掘机安全技术操作规程
- 4安全工程师案例分析复习要点:安全管理
- 52015年咨询工程师《项目决策分析与评价》每日一练4.4
- 6基坑排水采用的形式
- 7工艺设计基础知识培训 阀门的设置 45p
- 82015年招标师考试法规与政策:评标委员会的法律责任
- 9水、电源和其他动力条件调查内容表 蒸汽
- 102015年安全工程师安全生产法:矿山开采安全保障的规定
- 11涂料装饰工程质量管理对策 内容
- 122013年二级建造师《法规》:企业资质等级许可制度
- 13工程咨询概论知识点:我国工程咨询业的历史回顾
- 14一级建造师管理与实务复习要点:液态水
- 15安全工程师生产法复习资料——制定、修订标准的建议
- 16变形测量点的具体内容都有那些
- 17【达江解惑三】与名师对话 让我们一起从平凡走向成功
- 18某园林绿化工程施工组织设计47p
- 19[河南]桥梁工程立柱施工工法
- 20斗轮机施工措施
- 212015年安全工程师《管理知识》:应急预案的基本结构
- 222015年沈阳安全工程师报名时间
- 23具有发生滑坡条件的斜坡治理方法
- 24二级建造师考试复习总结:施工测量的内容和方法
- 25土方路堤填筑施工
- 26燃气管道的试验方法
- 272015年招标师:货物的价格特征和需求
- 282015年招标师考试答疑:编辑需要做哪些工作?
- 29水电工程管理与实务:生产安全事故的应急救援及调查处理
- 302010年PMP美国项目管理考试习题及答案八
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼