PMP认证考试练习题及参考答案(二十二)
1. project life cycles provide a better means of measurement of progress and control. the four phases of a project are conceptual development,
_____, _____, and _____.
a. preliminary planning, detail planning, closeout
b. implementation, reporting, termination
c. development, implementation, termination
d. execution, reporting, finishing
e. implementation, termination, post-audit review
ans: c
2. response planning is the responsibility of the functional areas and considers
a. mitigation.
b. deflection.
c. contingency planning.
d. unforeseen occurrences.
e. all of the above.
ans: ehttp://ks.examda.com
3. the definitive terms of a contract are written during which of the following contract phases?
a. contract phase
b. post-award phase
c. award phase
d. pre-award phase
e. requirement phase
ans: c
4. the sending or conveying of information from one place to another is the process of
a. networking
b. transmitting
c. interacting
d. promoting
e. interfacing
ans: b
5. which of the following types of cost are relevant to making financial decisions:
a. sunk cost
b. opportunity cost
c. material cost
d. a and c onlywww.Examda.CoM
e. b and c only
ans: e
6. in preparing a good project definition, experienced project managers will:
a. concentrate mainly on the end product rather than costs or benefits. these come later.
b. realize that only the "tip of the iceberg" may be showing. as a project manager, you must get beneath it.
c. understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.
d. try to convert objectives into quantifiable terms.
e. all of the above
ans: e
7. in which of the following is the cost of risk hidden by the contractor?
a. firm fixed price contract
b. fixed price plus incentive
c. cost plus fixed price
d. cost plus percentage of cost
e. a and b
ans: d来源:考试大网
8. management of a certain building was receiving complaints about slow elevator service. the solution adopted was to add mirrors in the
lobbies to reduce boredom while passengers waited. this is an example of _____ .
a. kepner-tregoe method
b. potential problem analysis
c. decision analysis
d. creative problem solving
e. none of the above
ans: d
9. pure risk differs from business risks because pure risk's _____ .
a. include chances of both profit or loss associated with the business.
b. include chances of loss and no chances for profit associated with the business.
c. must incur personal loss with business liability.
d. must incur business liability associated with loss of pure profit.
e. b and c
ans: b来源:考试大
10. the actual configuration of a pert/cpm network _____ the amount of resources that can be devoted to the project.
a. increases.
b. is not affected by
c. does not require
d. is heavily dependent upon
e. is the only means of determining
ans: d
11. the following types of costs are relevant to making a financial decision except:
a. opportunity costs
b. direct costs
c. sunk cost
d. unavoidable costs
e. none of the above
ans: c
12. the standard types of communication include all but
a. written
b. verbal
c. telepathic
d. nonverbal
e. none of the above
ans: c
13. _____ of the extra costs of the project can often be attributed to a lack of quality.
a. 0.12
b. 0.15
c. 0.2
d. 0.25
e. less than 10%
ans: c
14. a budget estimate should give the manager cost data accurate to within:
a. -5 to +10 percent of actual cost
b. -25 to +75 percent of actual cost
c. -30 to +75 percent of actual cost
d. -10 to +25 percent of actual cost考试大论坛
e. none of the above
ans: d
相关练习题:
PMP认证考试最新练习题及参考答案汇总
精品推荐:
PMP全真试题精选
欢迎进入在线试听:项目管理网上辅导,热招中!!
更多信息请进入:项目管理海量题库 考试大项目管理论坛
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1安全工程师安全生产法复习资料——档案管理与公告
- 2二建复习资料砌筑砂浆组成材料
- 32015造价员考试基础知识:开标与评标
- 4某污水处理厂及配套管网工程施工组织设计 96P
- 5湖北某车站站房项目生活区平面布置图
- 6二级建造师法规知识点:合同的变更
- 7《招标采购专业实务》考点归纳:编制工程概况
- 82015年监理工程师考试《理论与法规》试卷及答案
- 92013年二级建造师《法规》重点:诉讼时效
- 102015安全工程师考试考前冲刺试题精选(6)
- 112015年招标师《招标采购法律法规与政策》试题(7)
- 122015咨询工程师考试《咨询概论》预测试题(4)
- 13某城市花园环境景观工程施工组织设计
- 142012一级建造师《公路工程》:公路施工过程组织方法和特点(2)
- 152015招标师成绩:法规101分、管理106分、实务78分、案例78分
- 16受岩溶影响的地基的相关处理措施
- 172015年安全工程师生产技术模拟练习(9)
- 182015一级建造师《机电工程》讲义辅导(13)
- 192015年咨询工程师《分析与评价》每日一练(4.20)
- 202015年招标师《招标采购法律法规与政策》试题(17)
- 21嵌岩桩有哪些特点?
- 22而工程量则按实际完成的数量结算,这种合同属于什么合同
- 232015年招标师《招标采购案例分析》串讲资料下载(11)
- 24一级建造师管理与实务复习要点:液态水
- 25施工前应采用静载试验确定单桩竖向抗压情况
- 26杭州城站火车站预计八月开工十一亮
- 27安全工程师《法律法规》习题班讲义精选(55)
- 28经济政策与发展规划考点:区域规划的编制
- 292015年安全工程师考试《安全生产法》:危险化学品的运输
- 302013年二级建造师《法规及相关知识》每日一练(11.8)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼