PMP认证考试练习题及参考答案(二十一)
1. which of the following is referred to as payback period:
a. the number of periods required to recover the initial investment
b. the rate of return on the investment
c. the number of periods required to bring project cost back to the original budget, based on current performance
d. loan payment schedule
e. none of the above
ans: a
2. which one of the following is not an acquisition method?
a. advertising
b. invitation
c. negotiation
d. purchase考试大论坛
e. all are acquisition methods
ans: a
3. at least _____of the cost of quality are the direct responsibility of management.
a. 0.25
b. 0.85
c. 0.5
d. 1
e. 0.33
ans: b
4. fast tracking means to:
a. speed up a project through parallel tasks.
b. swap one task for another.
c. reduce the number of tasks if possible.
d. b and c.
e. none of the above.
ans: a来源:考试大网
5. formal written correspondence is mandated in which of the following situations:
a. product undergoes casual in-house testing
b. client requests additional work not covered under contract
c. project manager calls a meeting
d. b and c only
e. none of the above
ans: b
6. the delphi method is _____ .
a. used to derive a consensus arriving at a convergent solution
b. useful in determining probability relating to future events.
c. used with questionnaires based on established scenarios.
d. continued as an iterative process until a solution is reached.
e. all of the above.
ans: e
7. the positive value of conflict is underestimated. properly managed, conflict is a valuable tool, particularly when
a. a diversion is needed
b. conflictive situations are in their early stages and emotional involvement is low
c. conflictive situations are in their late stages and emotional involvement is high
d. conflict may cause a loss of status or position power
e.
ans: b
8. under the terms of 2/10 net 30, the buyer may:来源:考试大
a. deduct 10% of the invoice amount for payment within 30 days
b. deduct 2% of the invoice for payment within 10 days
c. incurs a penalty on 10% for payments more than 30 days late
d. settle the invoice with 2 equal payments; one within 10 days and the other within 30 days
e. none of the above
ans: b
9. which of the following can result in misinterpretation of the statement of work?
a. using imprecise language (i.e. nearly, approximately)
b. mixing tasks, specifications, special instructions and approvals
c. no pattern, structure or chronological order
d. wide variation in the size of tasks or details of work
e. all of the above
ans: e
10. amount at stake is the _____ .
a. function of planned time/real time project costs.
b. risk identified in successful project completions.
c. (standard project deviation + expected costs)/6
d. cost of investment loss + least cost to restore status quo.
e. inherent risk at conception altered by standard project deviations.来源:考试大网
ans: d
11. in communications management, to assimilate through the mind or senses (as in new ideas) is the process of
a. understanding
b. communicating
c. receiving
d. decoding
e. comprehending
ans: c
12. in general, the best long-lasting approach to settling project conflict is the _____ approach .
a. problem solving
b. compromise
c. withdrawal
d. smoothing
e. forcing
ans: a
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1如何防范政府采购风险
- 22015年一级建造师辅导资料:管道安装规定
- 3重庆市2015年安全工程师考试报名时间为5月16—6月6日
- 4简支变连续桥梁体系转换施工工法
- 5施工总承包管理模式与施工总承包模式的比较
- 6一级建造师项目管理复习要点:节点编号问题
- 72015年招标师考试招标采购案例分析复习指导(14)
- 8安全工程师《法律法规》习题班第八讲讲义(14)
- 9咨询工程师考试《工程项目组织与管理》模拟题(2)
- 102015年安全工程师考试《案例分析》练习题(7)
- 11超级计算机天河一号助力建筑信息领域
- 122015年咨询工程师《工程项目组织与管理》每日一练9.16
- 13国外贷款项目的管理
- 14陆地基本地貌有哪些类型?
- 15软土地基强夯法施工步骤
- 16引洞被复施工技术方案(一)
- 17山西省召开交通运输部公路隧道工程造价调研会
- 18【学员心声】学员通过二建 感谢建设工程教育网
- 19乐雅高速TJ11标大通寺新增跨路1#中桥架设完成
- 20道路绿化施工设计方案
- 21招标师职业水平考试:招标采购专业实务第九章练习题5
- 22碗扣式附墙电动升降钢管升降后的安全要求
- 232015年造价工程师考试《理论与法规》知识点总结(7)
- 24招标师职业水平考试:项目管理与招标采购第二章练习题13
- 252015年安全工程师《安全生产管理知识》备考模拟试题(2)
- 26一级建造师实务复习要点:架立钢筋
- 272015安全工程师《生产法及相关法规》提分试题(16)
- 28【招标师考试】项目管理与招标采购第二章:平行发包模式
- 29温州护国寺修建工程的施工组织设计方案
- 302015年咨询工程师《工程项目组织与管理》每日一练(12.12)
成都公司:成都市成华区建设南路160号1层9号