PMP认证考试练习题及参考答案(九)
1. financial compensation is the primary motivational tool for which of the following management theories of programs.
a. zero-defects program.
b. theory x management.
c. theory y management.
d. quality control circles.www.Examda.CoM
e. a and c
ans: b
2. in which of the following contract types is it easier to change the scope of the contract:
a. firm fixed price
b. fixed price plus incentive fee
c. cost plus percentage of cost
d. letter contract
e. none of the above.
ans: c
3. planning activities such that predetermined resource availability pools are not exceeded is called:
a. resource leveling.
b. manpower leveling.
c. resource limited planning.
d. manpower planning.
e. manpower contingency planning.
ans: c
4. the project charter:考试大论坛
a. expresses upper management commitment to the project.
b. provides that authority by which the project will be run.
c. establishes that organizational structure with the project.
d. specifies overall objectives and timeframe of the project.
e. all of the above.
ans: e
5. which of the following areas are addressed in risk identification:
a. environmental
b. technical
c. legal
d. all of the above.
e. a and b only
ans: d
6. which of the following types of power comes through the organizational hierarchy
a. coercive
b. reward
c. referent
d. legitimate
e. experthttp://ks.examda.com
ans: d
7. a calendar that identifies when a project may be performed on an activity is called a:
a. project calendar.
b. resource calendar.
c. milestone point.
d. key point.
e. work unit.
ans: a
8. charisma would be an example of _____ power.
a. legitimate
b. reward
c. coercive
d. expert
e. referent
ans: e
9. for every situation, several methods usually exist for effective communication to take place. which of the following is least likely to be used
for explaining to the team project planning guidelines?
a. project office memo
b. project office directive
c. project team meeting
d. formal reportwww.Examda.CoM
e. counseling sessions
ans: d
10. in the project environment, the individual ultimately responsible for quality control is:
a. the line workers who must strive "to do things right the first time" to avoid quality problems.
b. the company's quality control manager who must work with the project members to ensure the quality control program is effective.
c. the head of the production department who retains ultimate quality control responsibility for all the company's projects.
d. the project manager who has ultimate responsibility for the entire project.
e. the customer who must ensure that he is receiving a quality product from the vendor.
ans: d
11. in which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.
a. unit price
b. cost plus incentive fee
c. cost plus fixed fee
d. firm fixed price
e. b and d only
ans: d
12. middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?
a. project.
b. strong matrix.
c. weak matrix.
d. project coordinator.
e. project expeditor.
ans: c
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015一级建造师《市政工程》讲义摘要(15)
- 2工程咨询概论:政府投资补助
- 3消防工程师考试难度怎么样
- 4安全工程师辅导资料:电力施工安全管理5
- 5广州某学院综合楼施工临时用电平面布置图
- 6二级建造师注册流程
- 7一级建造师法规及相关知识复习要点:代位权的行使
- 8混凝土实心板有钢筋吗
- 9广西2015年注册安全工程师执业资格考试考务工作通知
- 10建筑外墙防水施工工艺(2011年 多图)
- 11天津今年同期建5条地铁线 2号线8月底全线贯通
- 122015年招标师考试招标采购专业实务考前复习指导(102)
- 132015年造价工程师考试辅导:Partnering模式
- 14某村镇给水管道工程施工组织设计
- 152015年造价工程师考试《理论与法规》知识点总结(3)
- 16安全工程师答疑精华:过罚相当原则
- 172015年造价工程师考试《计价控制》第二章讲义(3)
- 18安全工程师《法律法规》习题班讲义精选(96)
- 19安全工程师生产法复习资料——签订委托评价合同
- 20造价工程师技术与计量(土建)复习资料——汽车起重机
- 212015年咨询工程师《现代咨询方法与实务》练习题(22)
- 222015年招标师考试招标采购专业实务考前复习指导(58)
- 232015年咨询工程师《宏观经济政策与发展规划》每日一练(6.28)
- 242015招标师考试教材重点:合同法的基本原则
- 252015年咨询工程师《工程咨询概论》模拟题(18)
- 26软件项目管理如何加强土建施工现场管理的重要性?
- 272015年招标师:招标采购专业实务精选习题49
- 28工程造价的审核方法和审核内容有哪些
- 29建筑防水工程技术探讨
- 30某湿陷性黄土地区明挖隧道(投标)施工组织设计
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼