监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 甲方项目管理系统 | 签约案例 | 客户案例 | 在线试用
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

PMP认证考试练习题及参考答案(五)

申请免费试用、咨询电话:400-8352-114

1. there are two major types of reserves used on projects. the _____ is for (usually major) scope changes that were not considered as part of
the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.
a. management reserve, unplanned allowance fund.
b. management reserve, contingency.
c. contingency fund, management reserve.
d. unplanned allowance fund, budgetary reserve.
e. unplanned reserve, planned reserve.
ans: c

2. to determine what causes the majority of quality problems in a process, a very useful tool is the:
a. cause and effect diagrams.
b. flow chart.
c. control chart.
d. pareto chart.
e. trend chart.来源:www.examda.com
ans: d

3. which of the following is not part of contract administration
a. contract award
b. performance control
c. financial control
d. contract closeout
e. all of the above are parts of contract administration.
ans: a

4. a(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight,
storage and loss.
a. inventory control.
b. materials management.
c. procurement.
d. all of the above.
e. a and c only.
ans: b

5. expectancy theory as applied to project management implies that:
a. the team will work the hardest on those goals that are clearly explained by the project manager
b. the more rewards that the project manager provides, the better the performance of the team
c. team members will work hardest for those project goals that also bring satisfaction to personal goals
d. employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members
e. none of the above
ans: c

6. non-verbal communication includes:
a. body movement
b. gestures来源:考试大网
c. facial expressions
d. the way we move our hands
e. all of the above
ans: e

7. the formal invitation to submit a price for specified goods/services is usually referred to as:
a. request for proposal
b. request for quotation
c. tender invitation
d. bid invitation
e. a and b only
ans: b

8. the project scope/charter baseline includes:
a. summary of background conditions defining the project.
b. organization, authority and responsibility relationships.
c. functions to be performed.
d. resource requirement schedule including time estimates.
e. all of the above.
ans: e

9. which of the following is not an input to quality planning?
a. scope statement.
b. regulations.
c. work results.
d. standards.
e. quality policy.
ans: c

10. which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous
element has been completed?
a. pert
b. adm
c. pdm
d. all of the above.考试大(www.Examda。com)
e. a and c only.
ans: c

11. which of the following utility functions reflects risk-aversion:
a. uniform
b. increasing
c. decreasing
d. exponential
e. b and d only
ans: c

12. a deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as:
a. defective
b. defect
c. non-conformance来源:考试大网
d. poor workmanship
e. lack of fitness for use
ans: c

发布:2007-03-02 10:51    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件