PMP认证考试练习题及参考答案(三)
1. management decision-making includes:
a. analysis of alternatives.
b. revisions/replanning.来源:www.examda.com
c. resource allocation.
d. modification or updating of goals and objectives.
e. all of the above.
ans: e
2. the basic terminology for networks includes:
a. activities, events, manpower, skill levels and slack.
b. activities, documentation, events, manpower and skill levels.
c. slack, activities, events, and time estimates.
d. time estimates, slack, sponsorship involvement, and activities.
e. time estimates, slack time, report writing, life cycle phases, and crashing times.
ans: c
3. the project manager must receive reports and briefings from engineers, contracting officers, procurement personnel and marketing people.
the project manager's communication dilemma is one of:
a. encoding
b. decoding
c. choice of a medium考试大(www.Examda。com)
d. one-way communication
e. all of the above.
ans: e
4. the technique most commonly used to determine the profitability of a project includes _____ methods.
a. net present value (npv).
b. return on investment (roi).
c. discounted cash flow (dcf)
d. payout time and risk sensitivity analysis.
e. all of the above.
ans: e
5. which of the following are part of the purchasing cycle:
a. define need
b. prepare and issue purchase order
c. inspect incoming goods
d. all of the above.
e. a and b onlyhttp://ks.examda.com
ans: e
6. which of the following is closest to juran's definition of quality:
a. conformance to requirements.
b. fitness for use.
c. continuous improvement.
d. customer focus.
e. all of the above.
ans: b
7. a project element which lies between two events is called:
a. an activity.
b. a critical path method.
c. a slack milestone.
d. a timing slot.
e. a calendar completion point.
ans: a来源:考试大网
8. employee unions would most likely satisfy which level in maslow's hierarchy of needs?
a. belonging
b. self-actualization
c. esteem
d. safety
e. empowerment
ans: a
9. management calls a meeting to explain to all employees the new benefits package for the rank and file. this is an example of:
a. upward communication
b. downward communication来源:考试大网
c. one-way communication
d. two-way communication
e. none of the above.
ans: c
10. project management/project planning is most closely aligned with:
a. long range/strategic planning (5 years or more).
b. intermediate range planning (1 to 5 years)
c. short range/tactical planning (1 year or less).
d. all of the above.
e. b and c.
ans: e
11. the profitability and technical data studies are provided in report format to owners and funders for acceptance. this type of report, used to
solicit funding, is referred to as a(n) _____.
a. project feasibility study.
b. economic evaluation analysis.
c. risk management manual.
d. prospectus.
e. none of the above
ans: d
12. which of the following constitute juran's "quality trilogy":
a. planning, inspection, control.
b. planning, improvement, control.
c. planning, organization, control.考试大论坛
d. product, price, customer.
e. design, build, deliver.
ans: b
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1延延高速后塬坪隧道全线贯通 主体工程完工
- 2[安徽]2007年注册安全工程师执业资格考试成绩11月15日开始网上查询
- 3《招标采购法律法规与政策》第四章:投标有效期的确定
- 4南通滨湖公园—激光塔工程施工组织设计方案
- 52015年招标师全真模拟试题14
- 6《项目决策分析与评价》知识点:财务效益的确定
- 72015一级建造师《法规及相关知识》冲刺指导(6)
- 8排涝渠桥T梁施工方案
- 92015年咨询工程师《工程项目组织与管理》每日一练10.28
- 102015年咨询工程师《工程项目组织与管理》每日一练(5.28)
- 11二级建造师辅导:矿业工程施工合同管理
- 122015年注册咨询工程师《经济政策》习题(9)
- 132015年监理工程师考试《质量与进度控制》习题(11)
- 14《中华人民共和国招标投标法》考点精要五
- 152015年注册咨询工程师《工程咨询概论》模拟题(21)
- 16混凝土泵发现隐患应及时处理
- 17透视贫困县建设之难:拨款太少被迫掺水造假
- 18造价工程师复习资料:财务评价的作用
- 192015招标师考试:招标采购专业实务第七章详解3
- 20深孔爆破作业施工工法
- 21[青海省]06年安全工程师考试报名通知
- 222013年二级建造师《施工管理》每日一练(2.21)
- 232013年安徽二级建造师增项注册申请表
- 24规避自然灾害 加强农房抗震设防
- 25济南购房者怒揭房产中介的骗术看后让人恍然大悟
- 262015年招标师《法律法规》:从业资格制度
- 27"一种钢结构全过程跟踪系统"获国家实用新型专利授权
- 282015年咨询工程师《宏观经济政策与发展规划》每日一练(8.19)
- 292015年金昌造价工程师报名入口
- 30一级建造工程师市政公用工程管理与实务:燃气管道
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼