监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 甲方项目管理系统 | 签约案例 | 客户案例 | 在线试用
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

PMP认证考试练习题及参考答案(一)

申请免费试用、咨询电话:400-8352-114

1. communications is best described as:
a. an exchange of information.
b. providing written or oral directions.
c. consists of senders and receivers
d. effective listening.
e. all of the above考试大论坛
ans: e

2. fixed price contracts place more risk on the:
a. owner
b. buyer
c. seller
d. contractor
e. c or d
ans: e考试大(www.Examda。com)

3. life cycle costing is the total cost to the customer for the acquisition and ownership over its full life. life cycle costing categories include the cost
of _____, _____, and _____.
a. r & d, maintainability, operation and support.
b. r & d, production, operation and support.来源:考
c. acquisition, operations, maintenance.
d. production, operations, maintenance.
e. none of the above
ans: b

4. management by objectives assumes that the team:
a. is receptive to an unstructured environment.
b. does not require close supervision.
c. possesses a self directed philosophy
d. identifies with project objectives.来源:考
e. all of the above.
ans: e

5. quality may be defined as:
a. conformance to requirements.
b. fitness for use.
c. continuous improvement of products and services
d. appeal to the customer
e. all of the above except b来源:考
ans: e

6. since risk is associated with most projects, the best course of action is to:
a. cover all project risks by buying appropriate insurance
b. ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.
c. avoid projects with clear and present risks
d. eliminate all known risks prior to the execution phase of the project
e. identify various risks and implement actions to mitigate their potential impact
ans: e

7. the process of choosing/documenting the best approach to achieve the project objectives is part of:
a. the scope baseline.
b. scope authorization来源:考试大网
c. scope definition
d. scope planning.
e. all of the above.
ans: d

8. time management is the allocation of time in a project's life cycle through the process of:
a. planning
b. estimating.
c. scheduling.
d. controlling
e. all of the above.
ans: e

9. a comprehensive definition of scope management would be:
a. managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
b. approval of the scope baseline.http://ks.examda.com
c. approval of the detailed project charter.
d. configuration control.
e. approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
ans: a

10. cost plus percentage of cost contracts are more desirable for the:
a. owner
b. buyer
c. seller
d. contractor
e. c or d
ans: e

11. management styles associated with production environments, such as assembly lines commonly include:
a. a directing style of leadership.
b. a lack of confidence in their workerswww.Examda.CoM
c. assumption that workers lack ambition and dislike responsibility
d. a theory x style of leadership
e. all of the above.
ans: e

12. quality management:
a. is another name for careful inspections.
b. is inversely related to productivity.
c. is primarily the responsiblity of management.
d. is primarily the responsibility of the workers.
e. is essentially a motivational technique.
ans: c

发布:2007-03-02 10:52    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件