2010年pmp美国项目管理考试项目时间管理练习题及答案2
1. Increasing resources on the critical path activities may not always shorten the length of the project because:
A. No activities are time-dependent or resource-dependent
B. Activities are always scheduled with optimal number of resources
C. The Project Manager always selects original resources with the highest skill levels
D. Adding more resources may create additional work and produce inefficiencies
在关键路线上增加资源不会总是缩短项目的时间长度,这是因为:
A. 没有活动是依赖时间或依赖资源的
B. 总是以最佳的资源数量来安排活动
C. 项目经理总选择具有最高技能水平的初始资源
D. 增加更多的资源可能产生额外的工作并且导致效率低
2. Among the common types of scheduling techniques, task relationships are best illustrated using:
A. Networks
B. Gantt charts
C. Milestone charts
D. Work Breakdown structure
在计划安排技术的普通类型中用下列哪一项能最好地说明工作任务关系:
A. 网络
B. 甘特Gantt图
C. 里程碑图
D. 工作分解结构
3. Bar charts are most appropriate for:
A. Comparing actual to planned performance for each activity
B. Showing slack time
C. Showing critical path dependencies
D. Showing which activities can be rearranged in parallel
柱形图最适合于:
A. 对每项活动比较实际的与计划的绩效
B. 表示松弛时间
C. 表示关键路线的依赖关系
D. 表示哪些活动能被重新并行安排
4. Using the figure below, activity D has a latest start time of weeks and a
latest finish time of weeks.
A. 2, 10
B. 4, 12
C. 6, 14
D. 7, 15
利用下图数字计算, 活动 D 最迟开始时间是周和最迟完成时间是周
A. 2,10
B. 4,12
C. 6,14
D. 7,15
5. Which of the following does not represent the critical path?
A. Has a high degree of risk
B. Will elongate the project if the activities on this path take longer than anticipated
C. Must remain on schedule
D. Has the largest number of activities of any path
下列哪一项不代表关键路线?
A. 有高度风险
B. 如果这条路线上的活动要比所预期的花更长时间,项目时间将延长
C. 必须保持按进度
D. 任何有最大数目活动的路线
6. Networks are a result of the process and a key input to the process.
A. Activity definition, duration estimating
B. Activity sequencing, schedule development
C. Activity planning, schedule development
D. Activity sequencing, duration estimating
任务网络是过程的一个结果和是对过程的一项关键的输入
A. 活动定义, 工期估计
B. 活动排序,进度制定
C. 活动规划,进度制定
D. 活动排序, 工期估计
7. Which method shown below would normally not be used for shortening the schedule?
A. Crashing
B. Changing the scope
C. Performing activities in parallel rather than in series
D. Resource leveling
下面哪一方法通常不会被用来缩短进度?
A. 赶工
B. 变更范围
C. 以并行方式而不是序列方式来实施进行活动
D. 资源平衡
8. In a start-to-start relationship between two tasks not on the critical path, the project team determines that the start of the successor task must be delayed 3 days after the start of its predecessor. This delay is referred to as
A. Slack
B. Free float
C. Level float
D. Lag
在非关键路线上的二件工作之间的开始到开始关系中项目团队认为: 在前序工作开始之后, 后序工作的开始时间要被延迟3天这种延迟被称为
A. 时差
B. 自由时差
C. 水平时差
D. 滞后
9. In some Arrow Diagramming Method (ADM) networks, the project manager may be required to indicate logic relationships that do not consumer resources or time. These relationships are shown by using:
A. Critical path activities
B. Non-critical path activities
C. Slack time activities
D. Dummy activities
在箭线图示法(ADM) 网络中可能要求项目经理标明不消耗资源或时间的逻辑关系表
示这种关系可借助于:
A. 关键路线活动
B. 非关键路线活动
C. 有闲时间活动
D. 虚活动
10. A possible disadvantage of a bar chart is that it:
A. Lacks time-phasing
B. Cannot display more than one variable
C. Does not show activity interrelationships well on large complex projects
D. Cannot be related to manpower planning
柱形图的一个可能的缺点(劣势)是:
A. 缺乏时间定位
B. 不能展示出多个变量
C. 在大的复杂项目上,不能很好地表示出活动之间的相互关系
D. 不能与人力规划相联系
11. In the Arrow Diagram Method (ADM), the project element, which lies between two events, represents:
A. An activity
B. A critical path node
C. A slack milestone
D. A timing slot
在箭线图示法(ADM) 中位于二个事件之间的项目要素表示着:
A. 一项活动
B. 一个关键路线节点
C. 时差里程碑
D. 计时位置
12. Management has decided to “crash” a project in order to avoid penalty payments for late deliveries. Additional costs are expected. To crash the project, either overtime or additional resources should be assigned to:
A. All activities
B. Only those activities with the longest time durations C. Those activities on the critical path beginning with the lowest additional cost activities
D. Those activities with the greatest degree of risk
为了避免延迟交付的罚款, 管理层已决定要 "赶工"
预期会有附加的成本
为了要进行项目赶工,加班时间或额外的资源应该被安排到:
A. 所有的活动
B. 只是那些具有最长的持续时间的活动
C. 那些在关键路线开端上的具有最低的额外费用的活动.
D. 那些风险度最大的活动
13. All of the following processes are included in Project Time Management except:
A. Activity definition
B. Activity duration estimating
C. Resource planning
D. Schedule Control
所有下列过程都被包含在项目时间管理中,除了:
A. 活动定义
B. 活动时间估算
C. 资源规划
D. 进度控制
14. In building a ship, the painting task can be started but cannot be completed until all plumbing has been completed. This is an example of a:
A. Start to finish relationship
B. Finish to finish relationship
C. A relationship that shows slack
D. A finish to start relationship
在建造一条船时可以开始进行喷漆工作,但是必须在完成了所有的管线工作后, 才能完成喷漆工作
这是一个什么例子:
A. 开始完成关系
B. 完成完成关系
C. 表现出时差的关系
D. 完成开始关系
15. Using the figure below, the critical path is weeks.
A. 21
B. 22
C. 23
D. 24
利用下图所示数字,关键路线是周
A. 21
B. 22
C. 23
D. 24
16. Upon completion of the plan, your team determines that the schedule developed is too long. An analysis shows that the network diagram cannot be changed. You have additional resources available and some work can be easily shared with additional resources. Your best approach would be to:
A. Fast track the project
B. Conduct a Monte Carlo analysis
C. Use a parametric estimate
D. Crash the schedule
在完成计划后你的团队认为所制定的进度时间太长
一项分析表明不能改变工作网络图
你有附加的资源可利用并且一些工作能容易地分享附加的资源
你最好的方式会是:
A. 快速追踪项目
B. 引导一项 Monte Carlo 分析
C. 利用参数估算
D. 赶工进度
17. Once the logic of a network is laid out, the project manager will conduct a forward pass and then a backward pass through the network. Doing this will provide information on
the and the lead to the identification of the .
A. Slack for each activity, critical path
B. Slack for each activity, high-risk activities
C. Manpower shortages, high risk activities
D. High risk activities, non-critical paths
一旦制定出网络逻辑图,项目经理将会对网络进行顺推计算然后逆推计算提供关于的信息并且导致确认
A. 每项活动的时差,关键路线
B. 每项活动的时差,高风险活动
C. 人力短缺,高风险活动
D. 高风险活动,非关键路线
这样做将会
18. Inputs to activity duration estimating include all of the following except:
A. Expert judgment
B. Constraints
C. Assumptions
D. Resource capabilities
对活动工时估算的输入包括所有下列项,除了:
A. 专家判断
B. 限制因素
C. 假定
D. 资源能力
19. A project schedule whose start and finish dates reflect expected resource availability is called:
A. Resource limited schedule
B. Resource partitioning schedule
C. Resource leveling schedule
D. Resource quantification schedule
开始和完成日期反映着预期的资源可行性,这样的项目进度被称为:
A. 资源限制的进度
B. 资源分配进度
C. 资源平衡进度
D. 资源定量化进度
20. In the Arrow Diagramming Method (ADM), do not consume time or resources.
A. Nodes
B. Activities
C. Slack elements
D. Arrows
在箭线图示法(ADM) 中, 不消耗时间或资源
A. 节点
B. 活动
C. 有闲要素
D. 箭线
参考答案:
1、DDAAD BDDDC11、ACCBD DAAAA
相关链接:
2010年pmp美国项目管理考试项目时间管理练习题及答案1
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1咨询工程师《咨询概论》要点:企业投资项目核准和备案咨询
- 22015年招标师《项目管理与招标采购》名师讲义(7)
- 3烧结、焦化、耐火材科生产过程中存在的主要危险源及事故类别和原因
- 4造价员考试:如何提高复习效果
- 52015年注册咨询工程师《工程咨询概论》模拟试题(56)
- 6武汉至十堰城际铁路今年开工建设
- 72013年二级建造师《施工管理》每日一练(3.26)
- 82015年咨询工程师《宏观经济政策与发展规划》每日一练4.7
- 92015招标师职业水平考试科目法律法规:投标有效期的延长
- 10安全工程师安全生产法复习资料——岗位轮换
- 11杭州城站火车站预计八月开工十一亮
- 122015年招标师考试招标采购法律法规与政策辅导讲义五
- 13住宅小区施工现场平面布置图(基础、主体、装修)
- 14兰州小西湖立交桥项目正式开始制梁
- 15第三章投标第二十五条投标部分
- 162015年二级建造师《施工》重点:发包人责任
- 17安全工程师《生产管理》考前自测题(1)
- 18小窍门案例分析考场解题技巧
- 19巴彦淖尔公布2015安全工程师报名时间:6月23日—7月2日
- 20桥梁工程吊装作业——起重机械“十不吊”
- 21安全工程师生产管理复习要点:每年一次存储
- 222015年新疆造价工程师考试报名时间为6月10日-7月10日
- 23工程验收阶段施工组织主要内容表
- 24如何顺利通过二级建造师考试
- 252015年招标师招标采购专业实务重点解析3
- 262015年安全工程师《安全生产技术》每日一练(2.1)
- 27项目管理信息系统的生命周期
- 28某道路顶管工程施工组织设计
- 29招标师职业水平考试:项目管理与招标采购第四章练习题1
- 302015年二级建造师《市政》:进度控制的管理措施
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼