QUEST A contract originated bilaterally may be developed by _____ . 
A quotation request from suppliers 
B proposal request 
C bid invitation release 
D B and C 
E All of the above. 
参考答案:E

QUEST A legally binding document offered unilaterally is a _____ . 
A purchase order 
B scope of work description 
C contract stipulation 
D level of effort proposal 
E request for proposal 
参考答案:A

QUEST Fixed-price contracts place more risk on the _____ . 
A owner 
B contractor 
C seller 
D B and C 
E All of the above. 
参考答案:D

QUEST From an operating or functional perspective, there are various objectives of purchasing and materials management.  Which is not one of these objectives? 
A To buy competitively 
B To support company operations with an uninterrupted flow of materials and services 
C To develop reliable and effective sources of supply 
D To achieve maximum integration with the other departments of the firm 
E To attain approval from each department of every purchase 
参考答案:E

QUEST _____ is a receipt issued by a carrier for merchandise to be delivered to a party at some destination. 
A Proforma invoice 
B Inspection certificate 
C Packing list 
D Bill of lading 
E None of the above. 
参考答案:D

相关试题:

2010年PMP美国项目管理考试习题及答案26

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:53    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件