QUEST The review for the specification completeness is performed during which of the following cycles. 
A Award cycles 
B requirements cycle 
C requisition cycle 
D solicitation cycle 
E contractual cycle 
参考答案:C

QUEST In which of the following is the cost of risk hidden by the contractor? 
A Firm Fixed Price Contract 
B Fixed Price Plus Incentive 
C Cost Plus Fixed Price 
D Cost Plus Percentage of Cost 
E A and B 
参考答案:D

QUEST The definitive terms of a contract are written during which of the following contract phases? 
A Contract Phase 
B Post-Award Phase 
C Award Phase 
D Pre-Award Phase 
E Requirement Phase 
参考答案:C

QUEST The  _____   specification  delineates specific end use capabilities which can be tested in the acceptance procedure. 
A performance 
B functional 
C technical 
D base line 
E operational 
参考答案:B

QUEST Which one of the following is not an acquisition method? 
A advertising 
B invitation 
C negotiation 
D purchase 
E all are acquisition methods 
参考答案:A

相关试题:

2010年PMP美国项目管理考试习题及答案24

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:53    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件