2010年PMP美国项目管理考试习题及答案34

申请免费试用、咨询电话:400-8352-114

QUEST A deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as: 
A defective 
B defect 
C non-conformance 
D poor workmanship 
E lack of fitness for use 
参考答案:C

QUEST The formal invitation to submit a price for specified goods/services is usually referred to as: 
A request for proposal 
B request for quotation 
C tender invitation 
D bid invitation 
E A and B only 
参考答案:B

QUEST Which of the following is not part of contract administration 
A contract award 
B performance control 
C financial control 
D contract closeout 
E All of the above are parts of contract administration. 
参考答案:A

QUEST Which of the following is not part of the acquisition process: 
A source selection 
B invitation to bid 
C contract award 
D notice to proceed 
E All of the above are parts of the acquisition process. 
参考答案:D

QUEST Management reserve is generally intended to be used to: 
A implement additional unbudgeted scope 
B compensate for inaccurate estimates 
C cover major unforeseen catastrophes 
D cover unforeseen problems in the project 
E All of the above. 
参考答案:D

相关试题:

2010年PMP美国项目管理考试习题及答案33

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:53    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件