2010年PMP美国项目管理考试习题及答案13

申请免费试用、咨询电话:400-8352-114

QUEST Range estimating in determining cost risk probabilities requires  _____ . 
A an amount of financial exposure. 
B risks and opportunities ranked in order of bottom line importance 
C contingency requirements for expected level of confidence 
D probability of cost overrun occurrences 
E All of the above. 
参考答案:E

QUEST Standard deviation of project completion is _____ . 
A a relationship of the uncertainty of critical path activities. 
B an indicator of project end date target confidence 
C a function of critical path, leveling and project costs. 
D A and B 
E All of the above. 
参考答案:D

QUEST Which of the following does not contribute to increased Schedule Risk? 
A labor shortage 
B contractor claims 
C lack of access 
D sponsor scope changes 
E all may increase schedule risk 
参考答案:E

QUEST Screening of risk events for potential risk is known as _____ . 
A problem structuring. 
B risk identification 
C risk quantification 
D risk modeling 
E risk mitigation 
参考答案:B

QUEST The schedule risk is the _____ . 
A the accumulated "expected' durations which maintain project completion. 
B Critical Path adjusted by "high-risk" activity float. 
C highest risk path that maintains quality. 
D Critical Path when calculated with "most likely" duration. 
E highest risk path that contributes the most risk toward the project completion. 
参考答案:B

相关试题:

2010年PMP美国项目管理考试习题及答案12

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:53    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件