QUEST Communications is best described as: 
A an exchange of information. 
B providing written or oral directions. 
C consists of senders and receivers 
D effective listening. 
E All of the above 
参考答案:E

QUEST The purpose of project Risk Management is to: 
A Identify those factors that will adversely impact project objectives. 
B Assess the impact of adverse project factors. 
C Assess the probability of adverse project factors. 
D A and C 
E All of the above. 
参考答案:E

QUEST Project Risk Management is based on which of the following premises: 
A the future is unknown. 
B unknowns can result in risks or opportunities. 
C we cannot control risk events. 
D project risk impact can be measured and controlled 
E All of the above. 
参考答案:E

QUEST Risk mitigation is the process of _____ . 
A transferring risk to another party. 
B reducing uncertainty on the project 
C identifying all possible risk events 
D monitoring status and making adjustments 
E All of the above. 
参考答案:B

QUEST Risk exposure refers to _____ . 
A the amount at stake. 
B what might happen. 
C the likelihood of something 
D who is going to be held accountable 
E All of the above. 
参考答案:A

相关试题:

2010年PMP美国项目管理考试习题及答案10

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:53    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件