监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 甲方项目管理系统 | 签约案例 | 客户案例 | 在线试用
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

2010年PMP美国项目管理考试习题及答案20

申请免费试用、咨询电话:400-8352-114

QUEST Which of the following areas are addressed in risk identification: 
A environmental 
B technical 
C legal 
D All of the above. 
E A and B only 
参考答案:D

QUEST Monte Carlo simulation: 
A Was originally developed by Dr. Carlo 
B Is a European technique for assessing project risks 
C assumes the future risk events will occur at random according to predetermined probability distributions 
D is a technique to stimulate create risk event resolution 
E A, B and C only 
参考答案:C

QUEST Which of the following actions is an example of risk response: 
A adjust project parameters (scope, time, quality ...) 
B reduce the probability of potential project risk events 
C reduce the consequences of potential project risk events 
D wait until a problem actually happens, then deal with it in the most effective and efficient manner. 
E A, B and C only 
参考答案:E

QUEST Total project risk can be defined as: 
A the sum of the probabilities of project risks events times the sum of consequences of those risks 
B the sum of the products of each project risk event times its consequences 
C the sum of the consequences of all project risk events 
D the sum of the probabilities of all project risk events 
E 1 - the sum of the probabilities of all project risk events. 
参考答案:B

QUEST The utility of a risk seeker is: 
A negatively exponential 
B positively skewed 
C increasing 
D decreasing 
E symmetrical 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案19

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:53    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件