2010年PMP美国项目管理考试习题及答案19

申请免费试用、咨询电话:400-8352-114

QUEST Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? 
A concept 
B development 
C execution 
D conclusion 
E All of the above. 
参考答案:A

QUEST By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following: 
A Significantly reduce project risks 
B eliminate project risks 
C provide a rational basis for better decision making 
D identify risks, their impact(s), and any appropriate responses 
E None of the above. 
参考答案:B

QUEST A contractor estimates that a project has a 0.5 probability of $200,000 profit and 0.3 probability of $50,000 loss.  The expected monetary value of this project is: 
A ¥200,000 
B ¥150,000 
C ¥85,000 
D ¥50,000 
E None of the above. 
参考答案:C

QUEST Which of the following diagrams is most useful in impact analysis: 
A arrow diagrams 
B precedence diagrams 
C decision trees 
D Pareto diagrams 
E cause and effects diagrams 
参考答案:C

QUEST Which of the following risks are generally considered unpredictable: 
A business risk 
B financial risk 
C inflation 
D natural hazards 
E taxes 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案18

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:53    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件