2010年PMP美国项目管理考试习题及答案5

申请免费试用、咨询电话:400-8352-114

QUEST You are giving your team instructions on how to perform a new test which is different from the way that the team had performed it previously.  The best way to verify that the learn understands what you want is to: 
A obtain feedback 
B analyze the team's perceptions barriers 
C uses gestures in presenting the instructions 
D analyze the team's decoding skills 
E analyze the team's encoding skills 
参考答案:A

QUEST The project manager that allows and supports group discussions and decision making is called a(n) _____ manager. 
A autocratic 
B consultant autocratic 
C consensus 
D shareholder 
E None of the above. 
参考答案:C

QUEST Power games, withholding information, and hidden agendas are examples of-. 
A noise 
B communication barriers 
C indirect communication 
D mixed messages 
E All of the above 
参考答案:B

QUEST The main player in project communication is the 
A sponsor 
B project manager 
C functional manager 
D functional team 
E All of the above. 
参考答案:B

QUEST A recurring communication pattern within the project organization or company is called a: 
A free-form matrix 
B structured matrix 
C network 
D rigid channel 
E None of the above. 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案一百零四

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2