2010年PMP美国项目管理考试习题及答案九十

申请免费试用、咨询电话:400-8352-114

QUEST A project manager recently rewarded an individual with a promotion that carried with it a very small salary increase but substantially more responsibility.  The project manager appears to be appealing to the employee's _____  need. 
A Monetary 
B Physiological 
C Esteem 
D Self-actualization 
E Team-building 
参考答案:C

QUEST Employee unions would most likely satisfy which level in Maslow's hierarchy of needs? 
A Belonging 
B Self-actualization 
C Esteem 
D Safety 
E Empowerment 
参考答案:A

QUEST Using the situation the the Special window: 
A Productivity will increase 
B His decisions will promote high satisfaction among his team 
C His decisions will require less time 
D All of the above 
E A and C only 
参考答案:B

QUEST Participative Management: 
A involves the solicitation of information from all team members. 
B assumes that members avoid work and responsibility. 
C suggests the sharing of power and decision making. 
D employs a Theory X style of leadership. 
E A and C 
参考答案:E

QUEST The Japanese resource management model exhibits: 
A a cooperative spirit of goal setting. 
B non-specialized career paths 
C frequent changes in team assignments 
D a Theory Z style of management 
E All of the above. 
参考答案:E

相关试题:

2010年PMP美国项目管理考试习题及答案八十九

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3