QUEST The major difference between project and line management is that the project manager may not have any control over which basic management function? 
A Decision-making 
B Staffing 
C Rewarding 
D Tracking/monitoring 
E Reviewing 
参考答案:B

QUEST A good team leader must be concerned not only with  _____  but also with _____ . 
A Long term goals; short term goals 
B Organizational goals; personal goals 
C Legitimate power; referent power 
D Group efficiency; power and authority 
E Tasks to be accomplished; needs of the team members 
参考答案:E

QUEST In small companies, project managers and line managers are: 
A Never the same person 
B Always the same person 
C Sometimes the same person 
D Always in disagreement with each other 
E Forced to act as their own sponsors 
参考答案:C

QUEST A project manager who allows the team to make the majority of the decisions is demonstrating a(n)  ____ leadership style. 
A Laissez-faire 
B Boss-centered 
C Subordinate centered 
D Autocratic 
E Demographic 
参考答案:C

QUEST R & D project managers in high-tech companies most often motivate using  _____  power. 
A Expert 
B Reward 
C Referent 
D Identification 
E None of the above 
参考答案:A

相关试题:

2010年PMP美国项目管理考试习题及答案八十五

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:53    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件