2010年PMP美国项目管理考试习题及答案七十五

申请免费试用、咨询电话:400-8352-114

QUEST Which of the following is based on an individual identification with a more powerful person. 
A expert power 
B reward power 
C referent power 
D A and B. 
E A and C 
参考答案:C

QUEST Which of the following results are Win/Win conflict resolution? 
A compromising 
B forcing 
C problem solving 
D smoothly 
E withdraw 
参考答案:C

QUEST Which of the following organizations has the best technical project control? 
A matrix 
B functional 
C projectized 
D B and C 
E A and B 
参考答案:D

QUEST The functional organization is effective with a mature product or single product line. 
A TRUE 
B FALSE 
C参考答案:
D参考答案:
E参考答案:
参考答案:A

QUEST The strong matrix versus a weak matrix. 
A team members are more likely to be assigned to the project office in a strong matrix 
B strong matrix is more difficult to manage. 
C the balance of power has shifted away from the PM. 
D functional managers no longer has control over the technical processes. 
E All of the above. 
参考答案:A

相关试题:

2010年PMP美国项目管理考试习题及答案七十四

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件