2010年PMP美国项目管理考试习题及答案七十三

申请免费试用、咨询电话:400-8352-114

QUEST A team that is just forming needs: 
A An organization chart 
B Alternatives and choices 
C Structure and specificity 
D Orientation and organization 
E Opportunities for dialogue and conflict resolution 
参考答案:C

QUEST The capacity to get an individual or group to perform a given task is described as: 
A Authority 
B Power 
C Influence 
D Leadership 
E Motivation 
参考答案:E

QUEST A project manager believes that the best way to manage is to form a good, harmonious working relationship with the team, and high performance will follow.  The project manager could be defined as a _____   manager. 
A 1,9 
B 9,1 
C 1,1 
D 9,9 
E 5,5 
参考答案:A

QUEST Project leadership requires that the project manager pay attention simultaneously to the: 
A Tasks to be performed and needs of the team 
B Quantity and quality of the work to be performed 
C Efficiency and effectiveness of the team 
D Time, cost and performance deliverables 
E All of the above 
参考答案:E

QUEST Which of the following can the project manager use as a means of measuring project team effectiveness? 
A Absenteeism 
B Sponsor-approved salary increases 
C Efficiency of the team 
D Turnover of personnel 
E Grievances 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案七十二

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件