2010年PMP美国项目管理考试习题及答案八十二

申请免费试用、咨询电话:400-8352-114

QUEST In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review? 
A Not working directly with the assigned functional employees 
B Employees spend only a short amount of time assigned to the project 
C Not being knowledgeable enough to evaluate employees on technical judgment 
D All of the above 
E A and B only 
参考答案:D

QUEST The behavioral responsibilities of a project manager may also include dealing with: 
A The public 
B Regulatory personnel 
C The legal environment 
D Environmental issues 
E All of the above 
参考答案:E

QUEST Which of the following fall(s) under the responsibilities of a project manager? 
A Labor relations with project personnel 
B Affirmative action 
C Personnel training 
D Discrimination and equal employment opportunity 
E All of the above 
参考答案:E

QUEST Team members want to work for a project manager that can provide them with career path planning.  In which organizational form is career path planning difficult for project employees? 
A Matrix 
B Pure project 
C Project coordinator 
D Project expediter 
E Classical/traditional 
参考答案:B

QUEST The Delphi Method is well-suited for: 
A Decision-making 
B Forecasting 
C Overhead rate estimating 
D All of the above 
E A and B only 
参考答案:E

相关试题:

2010年PMP美国项目管理考试习题及答案八十一

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件