QUEST The core function of the project manager is 
A Systems design 
B Client interfacing 
C Quality assurance 
D integration 
E参考答案:
参考答案:D

QUEST Situations calling for a matrix organization include outside pressure for dual focus,  _____ and pressure for high information processing capability. 
A Pressure for clear accountability 
B Pressure for reduced duplication of effort 
C Pressure for shared resources 
D Pressure for formalized communication 
E参考答案:
参考答案:C

QUEST Advantages of the functional (hierarchical) form of organization include  _____ and creation of technical competence. 
A Ease of horizontal coordination 
B Clearly defined authority 
C High information processing capability 
D Single voice to customers 
E参考答案:
参考答案:B

QUEST History has shown that project managers can be trained in a combination of ways.  Which method is usually preferred by most companies? 
A Experiential learning, on-the-job 
B Formal education and special course (degreed programs) 
C Professional activities, seminars 
D Individual readings 
E None of the above 
参考答案:A

QUEST Which of the following organizational forms would be likely to have an individual with the title of Vice President for Project Management? 
A Classical / traditional 
B Pure project 
C Matrix 
D Project coordinator 
E None of the above 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案八十

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件