监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 甲方项目管理系统 | 签约案例 | 客户案例 | 在线试用
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

2010年PMP美国项目管理考试习题及答案七十九

申请免费试用、咨询电话:400-8352-114

QUEST The project team form of organization confers both advantages and disadvantages.  Disadvantages of the project form include: 
A Conflict in authority between project manager and functional managers 
B Dual allegiance on part of team members 
C Complex prioritization of resources 
D Loss of developed procedures on project dissolution 
E All of the above 
参考答案:E

QUEST In general, groups will ____ the average individual problem solver on problems with multiple stages. 
A Perform better than 
B Perform worse than 
C Take less time than 
D Do about as well as 
E参考答案:
参考答案:A

QUEST Which of the following would most likely not be an essential objective of a project team kick-off meeting 
A Create a project technology master plan 
B Get team members to know one another 
C Identify project problem areas 
D Obtain individual and group commitments 
E Identify the project coordinator 
参考答案:A

QUEST In which type of organization is team building likely to be most difficult? 
A Functional 
B Projectized 
C Matrixed 
D Project expediter 
E Project coordinator 
参考答案:C

QUEST Management of a certain building was receiving complaints about slow elevator service.  The solution adopted was to add mirrors in the lobbies to reduce boredom while passengers waited.  This is an example of _____  . 
A Kepner-Tregoe method 
B Potential problem analysis 
C Decision analysis 
D Creative problem solving 
E None of the above 
参考答案:D

相关试题:

2010年PMP美国项目管理考试习题及答案七十八

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件