QUEST A budget estimate should give the manager cost data accurate to within: 
A -5 to +10 percent of actual cost 
B -25 to +75 percent of actual cost 
C -30 to +75 percent of actual cost 
D -10 to +25 percent of actual cost 
E None of the above 
参考答案:D

QUEST The following types of costs are relevant to making a financial decision except: 
A opportunity costs 
B direct costs 
C sunk cost 
D unavoidable costs 
E None of the above 
参考答案:C

QUEST Which of the following types of cost are relevant to making financial decisions: 
A sunk cost 
B opportunity cost 
C material cost 
D A and C only 
E B and C only 
参考答案:E

QUEST In which of the following cost estimating techniques are statistics models used: 
A nonparametric cost estimating 
B parametric cost estimating 
C life cycle cost estimating 
D bottom-up estimating 
E All of the above. 
参考答案:B

QUEST Under the terms of 2/10 net 30, the buyer may: 
A deduct 10% of the invoice amount for payment within 30 days 
B deduct 2% of the invoice for payment within 10 days 
C incurs a penalty on 10% for payments more than 30 days late 
D settle the invoice with 2 equal payments; one within 10 days and the other within 30 days 
E None of the above 
参考答案:B

相关试题:

2010年PMP美国项目管理考试习题及答案四十四

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件