2010年PMP美国项目管理考试习题及答案五十二
QUEST An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:
A Higher salaried employees were assigned.
B Overtime was required.
C The overhead rate increased.
D Employee salaries had increased.
E Any of the above
参考答案:E
QUEST During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:
A The project will be completed late.
B The critical path has been lengthened.
C the costs are being overrun.
D Overtime will be required to maintain the original critical path.
E None of the above.
参考答案:E
QUEST Using the situation stated in the Special window, the total price variance of direct material is:
A ¥80,245
B ¥-4,236
C ¥-3,479
D ¥1
E ¥83,994.00
参考答案:C
QUEST Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A Become worse, become worse
B Become worse, improved
C Improved, increased
D Improved, become worse
E None of the above are correct
参考答案:E
QUEST A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.
A Trend line.
B Trend analysis.
C S curve.
D Percent completion report.
E Earned value report.
参考答案:C
相关试题:
2010年PMP美国项目管理考试习题及答案五十一
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015年咨询工程师知识点:目标评价的层次
- 2建筑工程施工组织设计常用资料
- 3深基坑施工排水机具的选用
- 4一级建造师管理与实务复习要点:孔道压浆
- 5地基设计有哪些原则?
- 6成昆铁路米易至攀枝花段线路走向确定
- 7听课过程中遇到的报错问题
- 8景观大道施工组织设计104p
- 9决策分析与评价考点:风险评估
- 102015年招标师考试招标采购案例分析复习指导(23)
- 11项目管理与招标采购第四章:工程咨询服务项目的范围
- 12兰渝铁路某标某隧道(实施)施工组织设计
- 13注册咨询工程师《工程咨询概论》预测试题(1)
- 14冬季混凝土搅拌车保养维修中不要犯的几个错误
- 15一级建造师管理与实务复习要点:回转钻
- 16一级建造师工程经济复习要点:所得税率的计算
- 17施工企业工程项目的信息化管理
- 18沪昆高铁湖南段重点控制工程隧道贯通
- 19安全工程师答疑精华:先导式
- 20水利水电工程就业方向
- 21编制投标书常见的115个错误(十五)
- 22安全工程师法规复习要点:四不放过”原则
- 232015年安全工程师考试题库《生产技术》(7)
- 24湖南机械教您如何操作混凝土输送泵
- 252015年咨询工程师《宏观经济政策与发展规划》每日一练(12.8)
- 26国家发改委关于注册安全工程师收费标准的通知(考试介绍)
- 27带压密封施工过程中的安全性问题
- 28土方量批量计算方法探讨
- 29耽误混凝土搅拌车寿命本领
- 302015年呼伦贝尔造价工程师现场审核地点及时间
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼