监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 甲方项目管理系统 | 签约案例 | 客户案例 | 在线试用
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

2010年PMP美国项目管理考试习题及答案四十

申请免费试用、咨询电话:400-8352-114

QUEST Value engineering/Analysis is the systematic use of techniques which does not include _____. 
A establishing values for required functions 
B provide the required functions at the lowest overall cost. 
C identifies the required function of an item 
D seeks to trade performance for cost 
E None of the above. 
参考答案:D

QUEST The ability to achieve cost savings is inversely proportional to _____. 
A the earned value achieved to date 
B the estimated costs to complete 
C empowerment to the P.M. 
D productivity 
E None of the above. 
参考答案:A

QUEST The estimated cost to complete (ETC) is _____. 
A BCWP/ACWP 
B the forecasted and final cost - cost to date 
C (ACWP-BCWP)/BCWP * 100 
D Total estimate - ACWP 
E None of the above. 
参考答案:B

QUEST Considering alternate suppliers is a form of _____. 
A Value engineering. 
B Risk Analysis 
C Contract Management 
D Project integration 
E All of the above. 
参考答案:A

QUEST You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid.  The correct conclusion is: 
A The project is operating at a favorable cost efficiency ratio. 
B the project is spending more than planned 
C the project is behind schedule 
D the project is ahead of schedule 
E B and C 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案三十九

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件