QUEST Time management is the allocation of time in a project's life cycle through the process of: 
A Planning 
B Estimating. 
C Scheduling. 
D Controlling 
E All of the above. 
参考答案:E

QUEST Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four.  The estimate at completion is: 
A $19K 
B $21K 
C $26K 
D $29K 
E indeterminate 
参考答案:C

QUEST Using the situation stated in the Special window,   a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____. 
A Become worse, become worse 
B Become worse, improved 
C Improved, increased 
D Improved, become worse 
E None of the above are correct 
参考答案:B

QUEST The computation for Cost Performance Index is: 
A BCWP/ACWP 
B BCWP-ACWP 
C BCWP-BCWS 
D ACWP/BCWP 
E ACWP-BCWS 
参考答案:A

QUEST When comparing the cost of competing projects, which of the following is typically NOT considered? 
A Opportunity costs. 
B Direct costs. 
C Sunk costs. 
D Indirect costs. 
E Burden rates. 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案三十七

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件