2010年PMP美国项目管理考试习题及答案二十八
QUEST On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:
A ¥-100
B ¥100
C ¥-150
D ¥150
E 85%
参考答案:C
QUEST A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. Calculate the variance:
A 1.50%
B 33.00%
C 75%
D 67%
E None of the above.
参考答案:B
QUEST Resource leveling will often affect the project by making it:
A Shorter.
B Longer
C More responsive to customer needs.
D A and C
E B and C.
参考答案:B
QUEST Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A 2
B 3
C 4
D 5
E 7
参考答案:C
QUEST Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.
A 2, 10
B 4, 12
C 6, 14
D 7, 15
E 9, 17
参考答案:A
相关试题:
2010年PMP美国项目管理考试习题及答案二十七
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1制造行业的研发多项目信息管理探讨
- 22013年四川二级建造师变更注册申请表
- 32015年监理工程师《工程合同管理》复习题(8)
- 4造价工程师案例分析复习要点:建设投资估算表
- 5[江苏]铁路隧道施工组织设计107页(双口对向掘进)
- 6后张法预制T梁制造及架设施工
- 7广东某出入境关口项目施工平面布置图(土建 装修)
- 8生产安全事故责任者所承担的法律责任
- 92015年福建造价工程师考试报名时间为6月28日-7月24日
- 10某路石灰土路基处理施工
- 11造价工程师案例分析复习要点:BEP(S)
- 122010年PMP美国项目管理考试习题及答案九十六
- 13倒虹吸施工
- 142015咨询工程师考试《项目组织与管理》模拟练习(15)
- 15一级建造师管理与实务复习要点:石灰土基层
- 162015年咨询工程师每日一练免费在线测试(2015.1.20)
- 17一级建造师公路工程管理与实务:钢筋绑扎
- 182015年度南通市造价工程师报名时间初定为5月-6月
- 192015年二级建造师《市政》重点:顶管施工的特点
- 202015年招标师考试《法律法规与政策》复习资料:第三章2
- 212015年安全工程师考试《生产技术》习题精选(7)
- 22PMP国家职业资格认证11月鉴定模拟题(1)
- 23安全工程师《法律法规》习题班讲义精选(106)
- 24铺装样式
- 25安全工程师安全生产法复习资料——取得生产许可、安全许可的程序
- 26工程硕士专业学位之环境工程领域简介
- 272013年二级建造师《施工管理》每日一练(5.7)
- 28土层锚杆的施工调查内容都包括哪些?
- 29焊接事故的预防措施
- 30黄土潜蚀地貌主要包括哪些?
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼