2010年PMP美国项目管理考试习题及答案三十七

申请免费试用、咨询电话:400-8352-114

QUEST The basic terminology for networks includes: 
A Activities, events, manpower, skill levels and slack. 
B Activities, documentation, events, manpower and skill levels. 
C Slack,  activities,  events, and time estimates. 
D Time estimates, slack, sponsorship involvement, and activities. 
E Time estimates, slack time, report writing, life cycle phases, and crashing times. 
参考答案:C

QUEST The utility of network-based schedules: 
A Reveals interdependencies. 
B Facilitates "what if" exercises. 
C Highlights critical activities. 
D Provides information on resource requirements, time requirements and tradeoffs. 
E All of the above. 
参考答案:E

QUEST The major disadvantage of a bar chart is: 
A Lack of time-phasing. 
B Cannot be related to calendar dates. 
C does not show activity interrelationships. 
D Cannot be related to manpower planning. 
E Cannot be related to cost estimates. 
参考答案:C

QUEST The most common types of schedules are Gantt charts, milestone charts, line of balance, and: 
A Networks. 
B Time phased events. 
C Calendar integrated activities. 
D A and C only. 
E B and C only. 
参考答案:A

QUEST Scheduling is the process by which decisions are made concerning: 
A Tasks to be accomplished. 
B Personnel/organization that will be assigned to accomplish the task. 
C Time when the tasks are to be completed. 
D All of the above. 
E A and C only. 
参考答案:E

相关试题:

2010年PMP美国项目管理考试习题及答案三十六

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件