2010年PMP美国项目管理考试习题及答案二十六

申请免费试用、咨询电话:400-8352-114

QUEST In crashing a task, you would focus on: 
A As many tasks as possible. 
B Non critical tasks. 
C Accelerating performance of tasks on critical path. 
D Accelerate performance by minimizing cost. 
E A and D. 
参考答案:C

QUEST Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task 
A 8 
B 8.8 
C 9.1 
D 9.7 
E 10.5 
参考答案:B

QUEST Using the WBS in the Special window,  an instance of a work package is: 
A Build house 
B Excavate 
C Prepare Foundation 
D B and C 
E None of the above 
参考答案:E

QUEST All of the following are categories of a milestone in a schedule except: 
A End date. 
B Contract dates. 
C Key events scheduled. 
D Imposed dates. 
E Task duration. 
参考答案:E

QUEST The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project. 
A Increases. 
B Is not affected by 
C Does not require 
D Is heavily dependent upon 
E Is the only means of determining 
参考答案:D

相关试题:

2010年PMP美国项目管理考试习题及答案二十五

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]