2010年PMP美国项目管理考试习题及答案十七

申请免费试用、咨询电话:400-8352-114

QUEST Make or buy decisions are usually made during the _____ phase of a project. 
A Conceptual 
B Development. 
C Implementation 
D Execution 
E Close-out 
参考答案:B

QUEST Historical records during close-out are useful to _____ and _____ for future projects. 
A Predict trends, highlight problems. 
B Analyze successes, shortfalls. 
C Analyze strengths, document results. 
D Support litigation, defend claims. 
E Justify results, set standards. 
参考答案:A

QUEST A clear definition of the user's needs serves as the direct basis for the: 
A Work breakdown structure. 
B Functional requirements. 
C Project cost estimate. 
D Selection of personnel. 
E Termination decision. 
参考答案:B

QUEST Middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure? 
A Project. 
B Strong matrix. 
C Weak matrix. 
D Project coordinator. 
E Project expeditor. 
参考答案:C

QUEST The project charter: 
A Expresses upper management commitment to the project. 
B Provides that authority by which the project will be run. 
C Establishes that organizational structure with the project. 
D Specifies overall objectives and timeframe of the project. 
E All of the above. 
参考答案:E

相关试题:

2010年PMP美国项目管理考试习题及答案十六

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件