QUEST In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs. 
A Increase, decrease. 
B Increase, increase 
C Increase, increase or decrease. 
D Decrease, decrease. 
E Decrease, increase. 
参考答案:B

QUEST Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____. 
A Allocation. 
B Partitioning 
C Leveling 
D Quantification. 
E None of above. 
参考答案:A

QUEST Smoothing out resource requirements from period to period is called resource _____. 
A Allocation. 
B Partitioning 
C Leveling. 
D Quantification 
E None of above. 
参考答案:C

QUEST Guidelines for estimating time durations include: 
A Assuming a normal  level of labor and equipment. 
B Assuming a normal work week. 
C Using consistent time units 
D Using past actual durations as guides. 
E All or part of each of the above. 
参考答案:E

QUEST Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed? 
A PERT 
B ADM 
C PDM 
D All of the above. 
E A and C only. 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案三十四

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件