2010年PMP美国项目管理考试习题及答案二十四

申请免费试用、咨询电话:400-8352-114

QUEST The most frequently used construct in Precedent Diagramming Method is: 
A Start to Start. 
B Finish to Finish. 
C Start to Finish. 
D Finish to Start. 
E Dummy activity. 
参考答案:D

QUEST The critical path is calculated by 
A subtracting the end date of task one from the start date of task two. 
B determining which tasks have the least amount of total slack. 
C totaling the time for all activities. 
D determining the shortest path through the network. 
E Determining which tasks have the most slack 
参考答案:B

QUEST Using the table in the Special window, Which task is completed? 
A dig hole 
B remove debris 
C survey 
D set forms 
E place concrete 
参考答案:B

QUEST Which may be employed to shorten a schedule without changing the scope of the task? 
A Fast tracking. 
B Crashing 
C Releasing resources earlier from tasks which were scheduled with a late start. 
D Alter to task priorities. 
E A or B 
参考答案:A

QUEST Resource leveling _____. 
A Allocates resources to activities to find shortest schedule within fixed resource limits. 
B Smoothes out resource requirements by rescheduling activities within their float time. 
C Smooths out resource requirements by substituting activities with unassigned resources. 
D Attempts to reduce resource requirements within a constraint on project duration 
E B or D 
参考答案:E

相关试题:

2010年PMP美国项目管理考试习题及答案二十三

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件