2010年PMP美国项目管理考试习题及答案三十三

申请免费试用、咨询电话:400-8352-114

QUEST The starting point in the development of a top-down PERT/CPM chart is the _____ . 
A Project specification tree. 
B Customer's deliverable list. 
C Customer's milestone dates. 
D Work breakdown structure. 
E Listing of customer team meeting dates. 
参考答案:D

QUEST The critical path in a network is the path that: 
A Has the greatest degree of risk. 
B Will elongate the project if the activities on this path take longer than anticipated. 
C Must be completed before all other paths. 
D All of the above. 
E A and B only. 
参考答案:B

QUEST The major difference between PERT and CPM networks is: 
A PERT requires three time estimates whereas CPM requires one time estimate. 
B PERT is used for construction projects whereas CPM is used for R & D. 
C PERT addresses only time whereas CPM also includes cost and resource availability. 
D PERT requires computer solutions whereas CPM is a manual technique. 
E PERT is measured in days whereas CPM uses weeks or months. 
参考答案:A

QUEST A calendar that identifies when a project may be performed on an activity is called a: 
A Project calendar. 
B Resource calendar. 
C Milestone point. 
D Key point. 
E Work unit. 
参考答案:A

QUEST Planning activities such that predetermined resource availability pools are not exceeded is called: 
A Resource leveling. 
B Manpower leveling. 
C Resource limited planning. 
D Manpower planning. 
E Manpower contingency planning. 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案三十二

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3